Self-levelling floor in Batumi for laminate, SPC vinyl and tiles
We pour self-levelling floors in Batumi over screed when it needs bringing to a flat plane for glue-down vinyl, laminate or large tiles. Labour costs from 14 ₾ per m², and the mix is priced separately according to the layer thickness. Before pouring we take levels with a laser level and check the strength and moisture of the base: a self-levelling layer evens out the surface, but it does not fix weak or damp screed.
from 14 ₾/m²pouring labour; the mix is extra, depending on the layer thickness. The final price is confirmed once agreed.
- Timeline: 2–3 days of preparation and 1 day of pouring for an apartment of about 45 m²; the floor covering goes down 3–14 days later, depending on the layer and the humidity
- Warranty: 2-year warranty on a self-levelling floor we have poured
Who it’s for
You are laying glue-down vinyl, and every wave in the screed would later show through the planks
The developer's screed in your white frame apartment wanders by a few millimetres between rooms
After the old tiles were removed, the floor was left with pits and adhesive residue
60×120 tiles need a flat plane that a thick bed of adhesive can no longer achieve
You want one floor level in the rooms, hallway and kitchen, with no small thresholds at the joins
What’s included
- measuring level differences with a laser level over the whole area
- checking screed strength and moisture, with photos
- dust removal, plus repair of cracks and pits as per the estimate
- one or two coats of primer, depending on how absorbent the base is
- a perimeter strip along the walls and around pipes and columns
- mixing with the water quantity from the data sheet and pouring without breaks
- going over the layer with a spiked roller to remove bubbles
- checking the drying with a moisture meter, and a certificate with straightedge readings
Self-levelling floor and screed: the difference
Screed sets the height of the floor: it is poured to guide rails in a layer several centimetres thick, and pipes, cable or soundproofing are hidden inside it. A self-levelling floor goes over the screed in a layer a few millimetres thick and brings its surface to a flat plane. The mix flows out by itself, and small waves, straightedge marks and pits disappear under a smooth surface.
We pour self-levelling floors in Batumi from cement-based mixes. The same name is used for polymer coatings based on epoxy resin, which become the finished floor themselves, but in apartments they are rarely ordered. Here we mean a levelling layer under a floor covering, and work with a thick base is described on the page about floor screed to guide rails.
When a self-levelling layer is needed, and when it isn't
- Under glue-down vinyl flooring it is needed almost always: thin vinyl follows every bump, and by the window, in light falling at an angle, it shows at once.
- Under laminate and click SPC vinyl we pour it if the gap under a two-metre straightedge is more than 2 mm. With a smaller gap the screed is already within tolerance, and laminate laying goes straight onto it.
- Under porcelain floor tiles in 60×60 and 60×120 formats we level when the screed wanders by a few millimetres: a wave like that can't be taken out with a thick bed of adhesive.
- After old tiles are removed, we fill the pits and the adhesive residue, if the screed under them is sound.
A thin layer can't strengthen a weak base: if the top of the screed crumbles or sounds hollow, the new layer will come away together with it. A level difference of more than 3 cm is also more honestly dealt with by screed than by pouring centimetres of expensive mix.
Preparing the base: strength, moisture, primer
The mix holds on to the screed, so first we check the screed itself: we scratch the top with a nail, tap it and measure its moisture with a moisture meter. We take the screed age required before pouring from the mix's data sheet, and for cement-based products it is usually at least 28 days. With developer's screed in a white frame apartment the pouring date is usually unknown, so we measure moisture at several points, including by the external wall.
We grind off a weak top and the laitance, open up and fill cracks, and remove the dust with a vacuum cleaner. Then we prime in one or two coats, depending on how much water the base absorbs. Primer seals the pores: otherwise the mix thickens before it has flowed out, and air from the screed rises through it and sets as craters. Along the walls and around pipes and columns we fix a perimeter strip, so that the layer doesn't butt against them and crack at the edge.
How we pour: levels, mixing, rolling
With a laser level we take readings across the whole area and set level pins to the height of the future layer. We calculate the thickness from the highest points of the screed: there the layer must be no thinner than the minimum on the mix's data sheet, usually 2–3 mm.
We mix with a paddle mixer and measure out the water for each bag according to the data sheet. Extra water thins the mix: the heavy filler settles, a weak film is left on top, and later it dusts and flakes under the floor covering. We pour in strips without a break, so that each new batch meets the still-liquid edge of the previous one, and immediately go over it with a spiked roller: it lets the air out and spreads the mix. Consumption on the data sheet is usually 1.5–1.8 kg per m² per millimetre, so a 5 mm layer over 40 m² takes 300–360 kg, or 12–15 bags of 25 kg.
Drying, and when to lay the floor covering
You can walk on a thin layer after a few hours, but the floor covering goes down later, after the time given on the mix's data sheet. For ordinary cement-based mixes it grows with the thickness: about three days for a layer up to 10 mm, a week for 10–30 mm and two weeks for 30–60 mm. These times are calculated for a warm, dry room, so in the wet months we go by the moisture meter, not the calendar.
A fresh layer doesn't need watering like screed: there is enough water in the mix, and the main thing is not to let draughts dry it out. For the first day we keep the windows closed and the layer out of the sun, and we don't point a space heater at it, otherwise the top dries before the body of the layer and a network of cracks appears. We start airing and running a dehumidifier on the second day.
How much a self-levelling floor costs in Batumi
Pouring a self-levelling floor costs from 14 to 18 ₾ per m², and that is labour only. The mix is priced separately: in our table it is 21–30 ₾ per m² at a normal layer thickness, and a thick layer needs more of it. If the screed needs grinding and repair, the preparation goes into the estimate as separate lines.
For comparison, screed to guide rails costs 40–66 ₾ per m² in labour plus another 30–42 ₾ for the mix at a 5 cm layer. So where a thin layer is enough, that is what we offer, and where the level difference is large, we price screed. Laying SPC vinyl over a self-levelling floor costs 25–36 ₾ per m². The final cost is set after measuring with a laser level and agreeing the estimate.
How we accept a self-levelling floor
We accept the layer once it has dried to the floor covering's moisture limit. We place the two-metre straightedge in several directions: under laminate and click SPC vinyl we allow a gap of up to 2 mm, and under glue-down vinyl no more than 1 mm. We tap the whole area and run a palm over the top: the layer must not sound hollow or leave dust on the hand. The straightedge and moisture readings go into the certificate with photos, and you see them before the floor covering goes down.
Stages and timelines
-
Measuring and decision
1 day
We take levels with a laser level, measure moisture and strength, and decide whether a self-levelling layer is enough or new screed is needed.
-
Base preparation
1–2 days
We remove a weak top, open up cracks and fill pits, and clear away the dust.
-
Primer and strip
1 day
We prime according to how absorbent the base is, fix the perimeter strip and set the level pins to the height of the layer.
-
Pouring
1 day
We bring all the bags up, mix to the data sheet, pour each room in one go and go over it with a roller.
-
Drying
3 to 14 days
For the first day we keep the windows closed and the layer out of the sun, then dry it to the floor covering's limit, checking with a moisture meter.
-
Inspection
1 day
We check with a straightedge, tap and scratch the top, record the moisture in the certificate and send you photos.
Local specifics in Batumi
The data sheet for a cement-based mix gives a maximum air humidity for pouring, usually around 80%. In the rainy months in Batumi the humidity can be higher than that even inside a closed apartment, so we dry the room with a dehumidifier in advance and close the windows on the day of pouring. In the wet season the layer itself also takes longer to dry, and we lay the floor covering only once the moisture meter says so.
In summer it is the other way round: wind from the sea through the balcony door and sun on floor-to-ceiling glazing overdry the top within a few hours. For the first day the windows stay closed, and we screen the sunny side.
In a new build the apartment sometimes has no water yet, while the mix needs an exact amount for each bag, so we bring water in canisters. We take the 25 kg bags up in the service lift during the hours the building's management company allows, and all at once: pouring a room can't be interrupted to wait for the next batch.
Materials and brands
We pour cement-based mixes from brands sold in Georgia: Ceresit, Knauf, Weber or Mapei. We choose the product for the layer thickness and the room, and take the permitted thickness, consumption and the time before the floor covering goes down from the data sheet of the mix bought for the job. In a bathroom we use only a mix that the manufacturer expressly approves for wet rooms.
We use primer from the same system as the mix, because the manufacturer has tested them together. The perimeter strip has to be foamed polyethylene, and masking tape is no substitute for it. We check the production date on the bags: a mix that has sat in a damp warehouse sets in lumps and flows less well.
What makes up the cost
Timeline: 2–3 days of preparation and 1 day of pouring for an apartment of about 45 m²; the floor covering goes down 3–14 days later, depending on the layer and the humidity
- carrying the bags up: service lift or stairs
What raises the cost
- a thick layer where the screed is out of level
- a weak screed top that we remove before pouring
- cracks and pits left after old tiles are removed
- a base for glue-down vinyl, with a stricter tolerance
What lowers the cost
- flat, sound screed that only needs a thin layer
- an open area with no partitions or pipes in the floor
We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.
Get an estimateGuarantees
2-year warranty on a self-levelling floor we have poured. If the layer comes away, cracks or dusts because of our work, we put it right at our own expense, and the procedure for taking up and relaying the floor covering on top of it is written into the contract. A thin layer reproduces a crack in the developer's screed, so we keep the readings and photos of the base before pouring in the handover file. The mix and primer carry the manufacturer's warranty.
Questions and answers
How much does a self-levelling floor cost in Batumi per m²?
Pouring costs from 14 to 18 ₾ per m², and that price excludes materials. The mix is priced separately: in our table it is 21–30 ₾ per m² at a normal layer thickness. If the layer turns out thick, more mix is used and that line in the estimate grows. Removing a weak screed top and repairing cracks are also separate items.
We send a preliminary estimate from photos and the plan within 24 hours on business days. The final cost is set after measuring with a laser level and agreeing the estimate: level differences don't show in photos.
How soon can laminate be laid on a self-levelling floor?
No sooner than the time on the mix's data sheet, and that depends on the thickness: a thin layer is ready in a few days, a thick one in one to two weeks. But these figures are for a dry, warm room. In the wet season in Batumi the layer takes longer to dry, so before laying we measure its moisture and compare it with the limit in the laminate instructions.
If the boards go down on a damp base, the moisture gets into the joints and the edges lift in the very first winter. We lay film under the underlay if the range manufacturer requires it.
Can a self-levelling floor be poured over old tiles?
Yes, if the tiles are firmly bonded. We tap each one, remove the loose ones and fill the voids with repair compound. Glaze is smooth and doesn't absorb water, so ordinary primer doesn't work on it, and we either grind the surface or apply a bonding primer with quartz sand.
The layer raises the floor, so we check the level against the thresholds and doors. In a bathroom we remove the old tiles in any case, because the waterproofing under them has to be redone, and there the self-levelling layer goes onto the screed.
Why does a self-levelling floor crack?
Most often because of water and drying. Extra water makes the mix easier to work, but a layer made from it shrinks more and cracks in a network. A draught, sun by the window or a space heater dries the top before the body of the layer. Without primer the screed draws water out of the mix, and the layer doesn't reach its full strength.
If a crack runs in a straight line across the whole room, it is usually a crack in the screed that the thin layer has reproduced. A fine network of cracks on a sound layer we grind and cover with the floor covering, and an area that has come away we remove and pour again.
Can a self-levelling floor be used in a bathroom?
Yes, but only with a mix that the manufacturer permits in wet rooms. A self-levelling layer in a bathroom doesn't replace waterproofing: we apply that on top of it, turned up onto the walls, and test it with water.
A self-levelling floor can't give a fall to a floor drain, because it flows out level. For a walk-in shower without a tray we make the sloped base with screed, and a self-levelling layer is the right choice under the bath, in the toilet and by the basin, where the floor needs to be flat.
Further reading
Send us a photo of the screed with a straightedge, and we'll tell you whether you need a self-levelling layer and how thick
We reply within an hour during business hours. Message us or leave a request: we’ll call you back, go over the details and suggest the next step.
Mon–Fri 10:00–19:00, Sat 11:00–16:00