Concrete frame house in Batumi
We build a concrete frame house in Batumi more often than any other type: the columns, beams and slabs are poured in concrete on the plot, and the walls between them are laid in aerated concrete, pumice blocks or clay blocks. The frame takes the seismic load and leaves you free to plan the layout and have large windows facing the sea. The shell of such a house costs from 690 ₾ per m², and for two storeys it usually goes up in 3–5 months.
from 690 ₾/m²shell: foundations, concrete frame, block walls and roof, excluding windows and services. The final price is confirmed once agreed.
- Timeline: the shell of a 150–200 m² two-storey concrete frame house usually takes 3–5 months, not counting the design and the permit
- Warranty: The frame, masonry and roof carry a 2-year warranty
Who it’s for
You're building a two-storey private house and want large windows facing the sea without wide sections of wall between them
You'd like to be able to change the layout over time without touching load-bearing walls
The plot already has a frame left by the previous owner, and you need to know whether it can be completed
You need open parking or a terrace under the house, with two living floors above
You want a masonry house, but without the cost of solid concrete walls
What’s included
- a review of the column grid and structural design together with the architect
- foundations to the ground survey: a slab or strip footings with ground beams
- columns, beams, slabs and stairs, with time for the concrete to cure
- infill masonry anchored to the columns and reinforced
- gaps under the beams and mesh where concrete meets block
- lintels and preparing the openings for windows
- a roof with gutters, and closing in the shell before the rainy season
- photos of the column and beam joints before every pour
You can see a cast-in-place concrete frame, or monolithic frame as it is called locally, on any high-rise building site in Batumi. In a private house on your own plot the scheme is the same, but the questions are different: where the columns will go, what the floor slabs will be like, how to make joints that hold the house together in a tremor, and what to do about parking under the house and balconies above the sea.
How a cast-in-place concrete frame works
The frame is made up of rigid frames: a column, the beam above it and the slab, tied together by reinforcement into a single joint. When the house sways, it is these joints that take the load, so the stirrups are spaced more closely where a column meets a beam, and the bars extend into the joint by the length set in the calculation. If the house is tall or elongated, the structural engineer adds concrete shear walls, usually around the stairs.
The infill walls don't carry the floor slabs, so the blocks for them are chosen on the basis of budget and facade. The foundation for the frame is usually a slab or strip footings tied together with ground beams, and the type is chosen from the ground survey.
The column grid and the layout
The column grid is set at the sketch stage, and it determines what the house will be like inside. In a private house we usually keep the spacing at 4–6 metres: that keeps the beams and slabs to a moderate depth, and a column ends up in the corner of a room or inside a wall rather than in the middle of the living room.
Floor slabs are made in two ways. With beams, the beam projects below the ceiling, but the slab is thinner and uses less concrete. A flat slab without beams gives a level ceiling, makes it easy to run ventilation underneath and to take windows right up to the top, but it is thicker and needs more reinforcement around the columns. For a living room glazed towards the sea the second option is often chosen, while the bedrooms keep the beams.
A column next to a panoramic window is worth spotting on the plan in advance, together with the architect. On paper it can be moved in an evening; after the pour, not at all.
Frame joints: what we photograph before the concrete goes in
In an earthquake the frame is held together by its joints, and the joints are then covered by concrete, so after the pour they can no longer be checked. That's why, before every pour of columns and slabs, the site foreman photographs what nobody will see afterwards: the stirrup spacing at the top and bottom of the column, where the stirrups are closer together than in the middle; the length by which the column bars extend into the slab and lap with the starter bars; and the spacers that hold the reinforcement at the right distance from the formwork panel.
We pour a column in one go over the full storey height, in layers, with a vibrator. If the concrete is dropped from a height without a chute, the coarse aggregate sinks to the bottom, cement paste is left at the top, and the joint under the beam ends up weak. We place a construction joint where the structural engineer put it, usually at the underside of the beam or the top of the slab, and before continuing we clean the cement film (laitance) off it.
How blockwork is tied to the columns, and why a flexible joint is left under the beam, is explained on the page about aerated concrete walls. The rules are the same for pumice and clay blocks, and the design sets the tie spacing for the particular block.
Parking under the house, balconies and cantilevers
On a slope and by the sea, people often want the house raised: parking or an open terrace on columns below, and two living floors with walls above. For a frame, this is the most awkward option. The floors filled in with masonry come out stiff, the lower one on bare columns is flexible, and in a tremor almost all the racking is concentrated there. The structural engineer calculates a storey like this separately: the columns are thicker, there is more reinforcement, and sometimes concrete walls are added at the ends, where they don't get in the way of cars.
A balcony or cantilever is the floor slab continued outwards. Out in the open, the edge of such a slab is cold and wet, so where it meets the house we build a thermal break into the slab, if the calculation permits, or insulate the cantilever above and below. Otherwise in winter the ceiling of the room next to the balcony gets damp. For the same reason we cover the columns on the facade with insulation. A long cantilever towards the sea is calculated for deflection, and the longer it is, the thicker the slab at its root.
Build sequence and shell timeline
The frame rises storey by storey: columns, then the formwork for the beams and slab, the pour and curing under props. We start the infill masonry on the lower floor once the slab above it is in place, and carry on while the concrete crew works higher up. That way the shell of a 150–200 m² two-storey house usually goes up in 3–5 months.
We bring the blocks in batches, one storey at a time, and keep them on pallets under plastic sheeting: a block soaked before it is laid goes on releasing water through the plaster for a long time. We try to get the roof on before the autumn rains, otherwise water stands on the slabs and runs down the fresh masonry.
You don't need to come out for every storey. Before each pour you get photos of the column and beam joints, and if you like, your own technical supervision engineer can inspect the frame before the concrete goes in.
When a different scheme is needed
A concrete frame is heavier than a steel one and needs access for a mixer truck. On a steep slope without a road, when adding a storey to an old house, or for a column-free living room 10–12 metres wide, steel is often simpler; this is covered in the comparison of a concrete frame and a steel frame. If you want brick walls or a brick facade, see the house with a concrete frame and brick walls: brick is heavier than block and changes the frame calculation.
For a small guest cabin or a summer house a concrete frame is overkill. There a light frame or masonry with reinforced ring beams is cheaper and faster.
How much a concrete frame house costs in Batumi
The shell of a concrete frame house costs from 690 ₾ per m² of floor area. The price includes the foundations, concrete columns, beams and floor slabs, block infill walls and the roof. Windows, building services and finishing are not included. For comparison, the shell of a house with solid concrete walls starts from 1,110 ₾ per m²: where a wall doesn't have to hold back the soil, block between the columns costs less than concrete.
After that the house goes through the stages in the table on the house construction page: white frame, ready for finishing, from 1,050 ₾ per m², and a mid-range turnkey house from 1,680 ₾ per m². Of the individual items, masonry stands out most in the estimate: a 30 cm aerated concrete wall with materials costs from 145 ₾ per m² of wall.
The price goes up with flat slabs and longer spans, cantilevers and balconies, brick or clay blocks instead of aerated concrete, and a stepped foundation on a slope. It comes down with a simple column grid at even spacing, repeated storeys and aerated concrete in the walls. We send a preliminary estimate from photos of the plot and a plan of the house within 24 hours on business days. The final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.
Stages and timelines
-
Column grid and structure
2–4 weeks
We check the architecture against the calculation: where the columns go, which slabs, where the shear walls are. We calculate the concrete, reinforcement and blocks.
-
Foundations
3–5 weeks
Earthworks, waterproofing, a slab or strip footing with reinforcement starter bars for the columns.
-
Ground floor frame
3–4 weeks
Columns, beams and slab. We photograph the joints before the pour and keep the props in place until the concrete gains strength.
-
Upper floors
3–4 weeks per storey
The same work one storey up, while the infill masonry goes ahead below.
-
Infill masonry
4–6 weeks
Block walls with anchors to the columns, a gap under the beam and lintels over the openings.
-
Roof and acceptance
2–4 weeks
Roof and gutters, after which we sign off the shell under a certificate together with you or your engineer.
Local specifics in Batumi
On the Adjara coast this is the most familiar scheme, so crews, formwork and concrete for it are easier to find than for any other method. The local difficulties lie elsewhere. On the slopes of Makhinjauri and Chakvi the foundations often step down, and the ground-floor columns end up at different heights. The short columns on the uphill side are stiffer than the long ones and take most of the load in a tremor, so the structural engineer evens them out with the column section or with shear walls.
Wind off the sea drives rain into the wall at an angle, and the joint between a column and the masonry on an exposed facade is the first to get wet. We cover these joints with mesh and insulation, and on the seafront we more often recommend a ventilated facade. Columns and slabs are easiest to pour from April to August, and we try to finish the masonry and roof before the September downpours.
Materials and brands
The concrete and reinforcement for the frame follow the structural engineer's specification, and the concrete comes from the plant with a certificate for each batch. For the infill we use aerated concrete on adhesive, pumice blocks or clay blocks on mortar: we choose the block to suit the facade and the budget, and check the batch for size and strength before unloading.
Anchors and ties between the masonry and the columns are stainless steel by the sea and galvanised further from the shore, and the mesh and bars for reinforcing the masonry are as the design specifies. We fill the gap under the beam with a flexible non-combustible material, and over the facade joints we lay alkali-resistant fibreglass mesh and render from the Ceresit or Weber system.
What makes up the cost
Timeline: the shell of a 150–200 m² two-storey concrete frame house usually takes 3–5 months, not counting the design and the permit
- the facade and windows, which are chosen separately from the frame
What raises the cost
- flat slabs without beams and longer than usual spans
- cantilevers, balconies and an open ground floor that is strengthened separately
- brick or clay blocks in the infill instead of aerated concrete
- a stepped foundation and columns of different heights on a slope
What lowers the cost
- a simple column grid with even spacing
- repeated storeys and standard joints
We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.
Get an estimateGuarantees
The frame, masonry and roof carry a 2-year warranty. We photograph the column and beam joints before the pour, and the photos go into the handover file together with the diagrams and the materials list. If we lay the wiring, water pipes and drains in the walls and floors, they carry a 5-year warranty.
Questions and answers
How much does a concrete frame house cost in Batumi?
The shell costs from 690 ₾ per m² of floor area: foundations, concrete columns, beams and slabs, block walls and the roof. Windows, building services and finishing are not included in this price. A house at the white frame stage costs from 1,050 ₾ per m², and a mid-range turnkey house from 1,680 ₾ per m².
The price is driven most by foundations on a slope, spans and cantilevers, the infill material and the facade. We send a preliminary estimate from a house plan within 24 hours on business days. The final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.
Can you complete a house frame started by another contractor?
Yes, once the frame has been surveyed. The engineer checks it against the design, if there is one, and examines the reinforcement starter bars, the concrete of the columns and slabs, rust and voids. A frame that has stood through several winters in the rain by the sea gets an especially careful check: exposed starter bars rust in that time.
Based on the results, the structural engineer sets out in writing what to keep, what to strengthen and what is better taken down. If there is no design, it is reconstructed from measurements. After that we draw up an estimate for completing the house and accept the frame under a signed certificate, so that the boundary of responsibility is clear on paper.
When can the walls be laid in a concrete frame?
Without waiting for the whole frame to go up. We start the masonry on a storey once the slab above it has gained strength and the props have been taken out from under it: in summer that is usually two to three weeks after the pour. Laying around the props is awkward, and a wall built up under a slab that is still deflecting takes the slab's weight.
We fill the top joint under the beam later, when the next slabs above that storey have been poured and most of the deflection has taken place. The bricklayers and the concrete crew work on different floors and don't get in each other's way, and the shell isn't held up waiting for one crew.
Can a wall be removed in a concrete frame house?
An infill wall usually can, as it doesn't carry the slabs. But look at the design before demolition: sometimes the structural engineer includes particular walls in the seismic calculation, and a concrete shear wall under plaster looks like an ordinary partition. We don't touch columns, beams or concrete walls without a calculation.
Check what is hidden inside, too. The diagrams in the handover file show where cables and pipes run in the wall. If the wall is being removed in a house we built, we'll tell you what runs through it and price the demolition and rerouting of the services as a separate job.
Can pipes and cables be run inside a cast-in-place floor slab?
Cables can, if this is planned before the pour: corrugated conduits with the cable are laid between the meshes to a layout, and the electrician checks the routes before the concrete goes in. We don't run water pipes or heating in the slab; they go in the floor screed, where a pipe can be reached without a jackhammer. Sleeves are set into the slab for soil stacks and ventilation.
A finished slab, beams and columns must not be chased: a chase cuts through the reinforcement or the cover over it. We drill a new hole in a slab only after the structural engineer has looked at where the bars run. We photograph all the routes before the pour, and they remain on the diagrams in the handover file.
Terms used on this page
- White frame
- An apartment after rough work: partitions, plaster, screed, electrical and water points, but no finishing or sanitary ware.
Further reading
Send us a house plan, and we'll suggest a column grid and price the shell within 24 hours
We reply within an hour during business hours. Message us or leave a request: we’ll call you back, go over the details and suggest the next step.
Mon–Fri 10:00–19:00, Sat 11:00–16:00