One apartment at different renovation stages: bare concrete, plastered walls and a finished room

Rough renovation of apartments in Batumi, ready for finishing

Rough renovation of an apartment in Batumi lays the groundwork for the finishes: partitions, electrics and water, plastering to guide beads, screed and waterproofing. We do it in black frame, in resale apartments after the strip-out, and in white frame where the walls and outlets don't match your plan. Labour with rough-work materials costs from 370 ₾ per m². Every layer is signed off by measurement, and we photograph the pipes and cables before they are closed up.

from 370 ₾/m²labour and rough-work materials up to white frame, including the service runs. The final price is confirmed once agreed.

  • Timeline: 5–7 weeks of work for a 1+1 apartment of about 45 m² from black frame; before the floor covering goes down, the screed still has to dry to the moisture meter limit
  • Warranty: 2 years on the work, 5 years on concealed pipes and wiring
Get an estimate

Who it’s for

  • Your apartment is in black frame, and the partitions need to go up to your own layout

  • In the developer's white frame you are moving walls or water outlets for a different kitchen and bathroom

  • In a resale apartment the strip-out has left bare walls and slabs, and the services need replacing entirely

  • You want to do the finishing later or with another crew, and first bring the apartment to flat walls and a dry screed

  • You live abroad and accept the work by photo: a straightedge on the wall, a gauge on the pipes, a tape measure by the runs

What’s included

  • setting out partitions, points and the finished floor level to the plan
  • partitions in aerated concrete or breeze block, plasterboard boxing and niches
  • consumer unit, cable runs and deep back boxes
  • water and drain pipework, pressure testing of the water supply
  • supports for an installation frame and a concealed mixer
  • wall plastering to guide beads
  • floor screed with a perimeter strip
  • waterproofing of the bathroom and balcony, tested with water
  • photos of concealed work and routing diagrams
  • construction waste removal

Prices: rough renovation

from 370 ₾/m²

WorkPrice
Rough work (to white frame)370–505 ₾/m²
Partition masonry (aerated concrete, breeze block)76–100 ₾/m²
Wall plastering to guide beads39–60 ₾/m²
Floor screed to guide rails40–66 ₾/m²
Electrical point (socket, switch, light fitting)42–66 ₾/point
Plumbing point (water or drain)96–145 ₾/point
Rough-work materials per m² of apartment120–155 ₾/m²

labour and rough-work materials up to white frame, including the service runs. The final price is confirmed once agreed.

Where rough renovation starts and ends

Rough renovation of an apartment in Batumi covers everything the finishes will later hide: partitions, electrics, water supply and drains, plaster, screed and waterproofing. In British terms, that is the first fix plus the plastering and screeding. It ends before the skim coat. By then the walls are flat and dry, the floor is ready for its covering, and the cables and pipes are brought out to every point and capped off.

We sign off each layer against its own check, and these checks are written into the acceptance checklist in the contract:

LayerWhat we check at sign-off
PartitionsPlumb, opening sizes, position against the setting-out from the grid lines
ElectricsBack boxes at the heights from the plan, labelled circuits in the consumer unit, a continuity check and insulation resistance test on every circuit
Water and drainsPressure during the pressure test, falls, caps on the outlets
PlasterThe gap under a two-metre straightedge, square corners where furniture will stand
ScreedLevels at several points in every room, no hollow spots when tapped
WaterproofingA dry ceiling below after 24 hours under water

In a black frame apartment, where there is only the structure of the building, we do every row of the table. In white frame the developer has already put in some of the layers, and the rough work comes down to moving walls and outlets and doing whatever is missing.

What to decide before the first block is laid

Rough work locks in decisions that are hard to change later. So before setting out we ask you to answer a short list of questions, and the crew doesn't start on site without the answers:

  • the furniture layout and a kitchen sketch, which decide where the sockets and water outlets go;
  • the models of toilet, mixers and shower: the installation frame and the concealed body of the mixer are fixed in the wall before plastering;
  • the type of ceiling in each room, because the air conditioning runs and the hood duct boxing will go in it;
  • the floor covering in each room, since its thickness sets the screed level;
  • underfloor heating, if you want it, and the positions of the indoor air conditioning units.

The ceiling is the decision people put off most often, although it determines how deep the runs have to be hidden and where the lights go. The comparison of stretch and plasterboard ceilings helps you see the difference.

Electrics: from the consumer unit to the back box

We fit a consumer unit (fuse box) with spare ways, because within a couple of years it almost always gains a circuit for a new appliance. We use copper cable in straight runs: vertically from each point to the ceiling or floor, and horizontally along them. Joints are made only in junction boxes that stay accessible, and we never bury a twisted joint in the plaster.

We use deep back boxes so that the connectors fit inside and the faceplate doesn't stick out from the wall. Low-voltage cables for internet and TV run separately from the power cables, at a distance, otherwise the signal picks up interference. For each future air conditioner we bring out power and a condensate drain, and for ceiling lighting we leave cable with spare length. We label the cable ends, and at the finishing stage the electrician fits the sockets by these labels without testing everything again.

Water and drains before they are closed up

We run the water supply from the stop valves at the inlet to each fixture. In an apartment with two bathrooms a manifold is more convenient: each fixture has its own valve on it, so a leak means shutting off one line, not all the water. The manifold goes behind an access hatch, and we leave no joints buried in the wall.

Before closing up, we test the system at a pressure above its working pressure and leave it like that for several hours. We photograph the gauge at the start and end of the test: if the needle hasn't moved, the joints are holding.

We lay the drains with a fall towards the riser and check it with a level on every section. At bends we use swept fittings, and at the riser we leave an access point. Pipes and the section of riser next to a bedroom or living room get wrapped in acoustic insulation: without it you hear every flush at night, yours and your neighbours'. We cap every outlet, from the washing machine to the sink, so that no mortar gets into them before the finishing stage.

Plaster and screed: tolerances instead of “roughly flat”

We plaster to guide beads and measure with a two-metre straightedge vertically, horizontally and diagonally. For paint and tiles we keep the gap to no more than 2–3 mm over the length of the straightedge, and for large-format tiles closer to the lower figure. In the corners where the kitchen, wardrobes and bath will go, we bring the walls to a right angle: in an out-of-square corner the worktop sits with a tapering gap, and the tiles end in cuts. Where blockwork meets a concrete column, we embed mesh over the joint, otherwise a crack will run straight along it.

With screed, the key thing is the level. We set it from the thresholds of the front door, the balcony door and the shower, and work it out separately for each floor covering: SPC vinyl is thinner than porcelain tiles, and underfloor heating adds its own thickness. If the levels aren't worked out in advance, you get a step where two rooms meet. Along the walls and around pipes we fix a perimeter strip. Without it the screed has no room to expand, especially with underfloor heating, so it cracks along the walls, and the sound of footsteps travels through the walls to the neighbours.

Waterproofing the bathroom and balcony

Waterproofing completes the rough cycle in wet areas. We apply it once the bathroom screed has dried out a little and the water outlets and floor drain are at their final levels: after it goes on, no more channels are cut in the floor or the bottom of the walls. Besides the bathroom and balcony, the same layer is needed under a washing machine and water heater in a storeroom, if there is a drain there.

We test the finished layer with water: we flood the floor for 24 hours, check the water level and the ceiling of the neighbours below, and only then photograph it and tile over it. On a balcony we take the layer under the door threshold, and the fall carries water to the edge of the slab. How many coats a shower needs, how high to take the membrane and how to build in the floor drain is covered on the page about bathroom renovation.

How much rough renovation of an apartment costs in Batumi

Rough renovation costs from 370 ₾ per m² of apartment floor area, with the usual range up to 505 ₾. The price covers labour and rough-work materials up to white frame condition, with the services run to your plan and the wet areas waterproofed. The skim coat, finishes and finishing materials are not included.

The estimate is priced item by item, and a few items move the total most. Wall plastering to guide beads costs from 39 ₾ per m², each electrical point from 42 ₾, and each plumbing point, water or drain, from 96 ₾. So an apartment with two bathrooms and dense wiring for the kitchen and air conditioners comes out closer to the upper end, and one with a simple layout and a single bathroom by the riser closer to the lower end.

The final cost is set after the site measurement and once the estimate is agreed. The price and timing of each stage are written into the contract, and unless the scope changes, the price of a stage doesn't go up.

If the finishing will be done later or by another crew

We hand over the rough stage with its own certificate, together with routing diagrams and photos of concealed work. From these, the next crew can see where the cables and pipes run and where it is safe to drill. Any comments on flatness are best raised when you sign off our stage: once someone else has applied the skim coat, it is hard to tell whose wave it is.

If the apartment will stand for several months before the finishing, especially in winter, it needs airing or a dehumidifier left running, and the water should be shut off at the inlet. The caps stay on the outlets until the finishing stage. Individual jobs, such as just the screed or just rewiring, can be ordered without the whole rough cycle: they are listed in the section on renovation and finishing works. In a resale apartment, the rough stage is part of a full renovation and starts with the strip-out.

Stages and timelines

  1. Decisions and setting out

    2–3 days

    We check the furniture, electrical and plumbing plans, and mark out the partitions, points and finished floor level on the walls and floor.

  2. Blockwork and framing

    1–2 weeks

    We build block partitions, put up plasterboard boxing and niches, and fit supports for heavy wardrobes and installation frames.

  3. Runs and pressure testing

    1–2 weeks

    We assemble the consumer unit, run power and low-voltage cables, and lay the water and drain pipes. The water supply is pressure-tested, and the runs are photographed with a tape measure.

  4. Plastering to guide beads

    1–2 weeks

    We level the walls, reinforce the joints between blockwork and concrete, and bring the corners square for the kitchen and wardrobes.

  5. Screed

    3–5 days

    We fix the perimeter strip, set the guide rails to the levels and pour the floor. Then the screed dries, and we check that it is ready with a moisture meter.

  6. Waterproofing and stage certificate

    4–6 days

    Once the bathroom screed has dried out a little, we apply the waterproofing and keep it under water for 24 hours. The stage is closed with a certificate and routing diagrams.

Local specifics in Batumi

In Batumi new builds with a cast-in-place concrete frame, the columns and some of the walls are concrete, with the reinforcement close to the surface, so we don't cut deep channels in them: we take the run into the floor or ceiling and lay the cable in flexible conduit. It is worth allowing for this in the electrical plan if a socket is drawn on a column.

In a tall building, water pressure differs from floor to floor. Before running the pipes we measure it at the inlet, and if it is higher than the mixers and washing machine are rated for, we fit a filter and a pressure reducing valve after the stop valves.

After plastering we take out the galvanised guide beads and fill the grooves. In humid sea air, and especially in gypsum plaster, the zinc coating gives way over time, and the steel rusts and shows through the paint as orange streaks. For the same reason, we use corrosion-protected fixings and mesh in the bathroom and on the balcony.

Materials and brands

For dry rooms we use Knauf gypsum plaster, and for the bathroom, the kitchen wall behind the sink and the balcony, cement-based mixes from Ceresit or Weber. Waterproofing is one Mapei or Ceresit system: the liquid membrane, corner tapes and pipe collars all come from one manufacturer, otherwise the layers may not bond well.

We build boxing and niches on Knauf metal studs, and in wet areas only from moisture-resistant board, such as Knauf or AK Bulut. The water supply is polypropylene or PEX (cross-linked polyethylene), and the drains are plastic pipes with rubber seals. With blocks and sand we check the batch itself, including the block dimensions, and its documents: the name on the pallet tells you little here.

What makes up the cost

Timeline: 5–7 weeks of work for a 1+1 apartment of about 45 m² from black frame; before the floor covering goes down, the screed still has to dry to the moisture meter limit

  • getting materials up: a service lift or the stairs

What raises the cost

  • many partitions, especially in blockwork
  • large differences in slab level and a thick screed
  • walls out of plumb that need a thick coat of plaster
  • many electrical points, and wet areas far from the riser

What lowers the cost

  • white frame where some of the walls and screed can stay
  • one bathroom by the riser and a simple layout

We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.

Get an estimate

Guarantees

Warranty: 2 years on work, 5 on pipes and cables in walls and floors.

The period runs from the date of the completion certificate and still applies if another crew does the finishing later. If that crew damages a pipe or cable while drilling, it is no longer a warranty case, which is why we hand over the routing diagrams together with the certificate.

Questions and answers

How much does rough renovation of an apartment in Batumi cost per m²?

From 370 ₾ per m² of apartment floor area, with the usual range up to 505 ₾. This price covers labour and rough-work materials: partitions, electrics and plumbing up to the points, plaster, screed and waterproofing of the wet areas. Materials account for roughly a third of the total.

An apartment with two bathrooms, block partitions and a thick screed will be closer to the upper end. We'll send a preliminary estimate from the plan and photos within 24 hours on business days. The final cost is set after the site measurement and once the estimate is agreed.

How can I check the quality of rough work from photos and video?

Ask for shots with a tool in them: a general view of the room shows very little. On a wall, a two-metre straightedge, with a gap visible under it or none. On the screed, a laser level and a tape measure at several points in the room. On the water pipes, the pressure test gauge at the start of the test and a few hours later. On the cable runs, a tape measure from the floor and from the corner, so the line can be found in the wall later.

We send shots like these in the weekly report, and at stage sign-off the foreman repeats on video any measurement you ask for.

Do walls need priming before plastering?

Yes, and the primer is chosen for the substrate. On smooth cast-in-place concrete we apply a bonding primer with quartz sand, otherwise the plaster holds poorly and eventually comes away in sheets. Aerated concrete and breeze block draw a lot of water out of the mix, so we prime them with a deep-penetrating primer to keep the plaster from drying out before it gains strength.

On external walls we use a primer with an antifungal additive: otherwise winter condensation in the corners turns into mould under the finishes. We start plastering once the primer is dry, taking the drying time from the technical data sheet; it is usually anything from a few hours to a day.

Where is the best place for the consumer unit in an apartment?

Usually in the entrance hall, close to where the cable comes in from the floor distribution board: the run is shorter and servicing is easier. You should be able to open the consumer unit without moving furniture, and it shouldn't be in a bathroom or in a storeroom with a washing machine, where it is damp.

We choose a height at which the breakers can be seen without a stepladder but children can't reach them. If the unit is recessed into the wall, we form the recess for it at the blockwork stage, with extra depth and spare ways for future circuits. A diagram with labelled breakers goes into the handover file.

Can water pipes be laid in the floor screed?

Yes, if the pipe in the screed has no joints at all. We lay unbroken lengths of polypropylene or PEX in corrugated sleeving or insulation: that way the pipe can expand with hot water without pressing on the mortar.

Before pouring, we pressure-test the system and photograph the run with a tape measure from the walls. We leave enough mortar over the pipes, otherwise the screed will crack above them. The manifold and all the joints are brought out behind a hatch, not into the floor.

Terms used on this page

White frame
An apartment after rough work: partitions, plaster, screed, electrical and water points, but no finishing or sanitary ware.

Further reading

Send us the apartment plan, and we'll price the rough renovation within 24 hours

We reply within an hour during business hours. Message us or leave a request: we’ll call you back, go over the details and suggest the next step.

Mon–Fri 10:00–19:00, Sat 11:00–16:00

Estimate within one business day

Step 1 of 3
Property type
Current condition
Step 2 of 3
When to start
    Step 3 of 3
    Preferred contact method

    How would you like to reach us?

    We’ll call you back at a time that suits you

    Preferred contact method
    Best time to call

    Search the site