A glulam house in Georgia is assembled from a factory house kit: the timber is glued together from kiln-dried lamellas, and the notches and openings are machine-cut to the design. It hardly settles, so the windows go in straight away and finishing starts as soon as the house is closed in. It is a sensible choice for a timber house lived in all year round or rented out, when the build is managed from far away. The shell costs from 1,980 ₾ per m², excluding windows and finishing.

from 1 980 ₾/m²foundations, walls from the factory kit, floors and roof, excluding windows. The final price is confirmed once agreed.

  • Timeline: a 150 m² glulam shell usually takes 1–2 months after the kit is delivered, and the factory sets the production time
  • Warranty: Our work from foundations to roof carries a 2-year warranty
Get an estimate

Who it’s for

  • You want a timber house and to move in the same year, with no pause for settling

  • You live abroad, and there is nobody to adjust the screw jacks and doors

  • The design has a double-height living room with floor-to-ceiling windows

  • You are building a house to rent out and want to open it for the coming season

  • You have found a house kit from a factory abroad and want it checked for Georgia

What’s included

  • A check of the factory's shop drawings by our structural engineer against the seismic code
  • Agreeing the openings, electrical routes and embedded items before production starts
  • Preparing the access, the unloading area and the crane for the kit's arrival
  • Acceptance of the kit against the schedule, with moisture readings and inspection of the ends
  • A slab or ground beam with an accurate top and anchors to the factory's diagram
  • Assembly of the walls, floors and rafters with slip joints
  • A roof with gutters, and preservative and wood stain on the facade
  • Photos of the anchors, the damp-proofing under the first course and the joints for the handover file

Prices: glulam

from 1 980 ₾/m²

WorkPrice
Glulam house shell1 980–2 400 ₾/m²
Turnkey glulam house3 000–3 600 ₾/m²
180–200 mm glulam wall, with materials and assembly (per m² of wall)690–840 ₾/m²
Timber lacquering or oiling27–36 ₾/m²
Slab foundation per m² of house footprint390–480 ₾/m²
Thermally broken aluminium windows, installed780–1 020 ₾/m²
Profiled timber house shell1 200–1 440 ₾/m²
CLT panel house shell2 220–2 760 ₾/m²

foundations, walls from the factory kit, floors and roof, excluding windows. The final price is confirmed once agreed.

People choose a glulam house when they want timber walls but aren't prepared to wait a year for the house to settle. Glulam is glued together from dry boards called lamellas, and it holds its size better than solid timber. The price for this is a higher cost and strict demands on the design: the house arrives from the factory as a set of numbered parts, and a mistake in the drawings can no longer be put right with a saw on site.

What a house kit consists of

Glulam is turned into a house kit by a machine: it planes the profile, usually a fine multi-tongue “comb”, cuts the notches at the corners, the grooves for the settling frames in the openings and the holes for the dowels. Every piece is marked, the kit comes with an assembly diagram, and the crew builds the walls by the numbers with almost no fitting.

For the walls we usually use 180–200 mm glulam. Floor beams, transoms and rafters are often made of the same glulam: it comes longer and straighter than solid wood and doesn't twist after installation. What comes from the factory and what we buy locally is fixed in the specification before the order.

Designing for the factory: what we decide before ordering

The factory turns the architectural design into shop drawings, breaking each wall down into individual timbers and joints. Our structural engineer checks them against the Georgian seismic building code and the ground on the plot, and at this step the anchoring to the foundations and the wall sections next to large windows often change. We don't take on a calculation that the factory made for its own country without this check.

Before the order goes into production, we settle questions that in a masonry house are usually left for later:

  • the size and position of every window and door, including the sill height;
  • the electrical routes: if the factory drills cable channels in the timber, the sockets will end up exactly where they were drawn;
  • the water and drainage entries, and the extracts from the bathrooms and kitchen;
  • the places for heavy items: kitchen units, the water heater, the TV.

Once the factory has started cutting the timber, moving a window means new timber and a new delivery. So you sign off the shop drawings as a separate stage.

Ordering the kit and accepting it on site

We have no production of our own: we order the house kit from a manufacturer for the specific design. Glulam may also be imported, so we name the manufacturer and the country the kit will come from in the estimate. The production time is set by the factory, and we find it out before the contract is signed, to know whether we can get the roof on before the autumn rains. If the kit comes from abroad, delivery and customs clearance are usually handled by the supplier, and we prepare the access, the unloading area and the crane for the lorry's arrival.

On acceptance we count the pieces against the schedule and inspect the packaging. If the wrapping is torn and the timber travelled wet, we record it in the acceptance report. We measure the moisture content, check the ends for delamination along the glue lines and match the markings to the diagram. Which questions about the adhesive to ask the manufacturer in advance we listed when comparing glulam and solid profiled timber. Until assembly the kit is stored under cover, raised off the ground on bearers, and we slit the factory wrapping at the bottom so that condensation doesn't collect under it.

Foundations for a house kit

The timber arrives with machine precision, and the foundations have to be just as precise. If the top of the plinth varies in height or the corners don't match on the diagonals, the first courses sit with gaps, and the error travels up the whole wall. So before the damp-proofing goes down, the site foreman checks the top of the plinth with a level and measures the diagonals, and the readings are attached to the stage certificate.

Most often we pour a cast-in-place slab with a plinth: it gives even support across the whole footprint and also serves as the base of the floor. On a slope it usually ends up as piles with a cast-in-place ground beam, and how the choice between them is made on different ground we described when comparing pile and slab foundations. The anchors for the bottom course are cast into the concrete to the factory's diagram, and the site foreman photographs them before the pour.

Assembly and finishing with no pause for settling

The walls of a kit go up quickly, and after delivery the shell is usually under its roof within a few weeks. Glulam hardly settles. Its thickness does still change slightly with the moisture in the air: it takes up water in summer and gives it up in winter with the heating on. So windows and doors still go into settling frames with a small gap, and the rafters and staircase still get slip joints, although the allowance there is much smaller than for profiled timber.

Finishing starts straight away. Inside, the timber is sanded and coated with oil or lacquer, and the bathrooms are built on a separate frame with moisture-resistant plasterboard, so that the tiles don't depend on the movement of the wood. On the outside we apply a preservative and a wood stain with UV protection.

Long beams and large spans

The lamellas are finger-jointed along their length, so a glulam member isn't limited by the length of a trunk, and it is used for beams that profiled timber can't span: a living room with no supports in the middle, a double-height space, a cantilevered canopy over a terrace. The beam sections, the supports under them and their connections to the walls are calculated by the structural engineer, and the factory cuts the beams from the same drawings as the walls, along with the pockets for the supports.

A long wall has its own limit. If in the design it runs further without cross walls than the calculation allows, it is braced with a short cross wall notched into it or with pairs of posts bolted through the wall, and space for them is built into the shop drawings. Floor-to-ceiling windows work in a similar way: the wider the opening, the less solid timber is left in the wall to hold the house in a tremor. So we agree the width of the glazing with the structural engineer before you sign off the shop drawings.

Glulam house in Georgia: when it is worth it

Glulam costs noticeably more than profiled timber, and we recommend it where the difference buys you time and less upkeep:

  • a year-round home you need to move into in the same year the build starts;
  • a house to rent out that has to take guests by the coming season, not after a year of settling;
  • the owner lives abroad, and there is nobody on site to adjust the doors and screw jacks;
  • a house with a glazed gable and large spans; how such a house is built on a masonry lower floor is described on the page about chalets.

If you like exposed beams with glass between them, take a look at half-timbered houses, where glulam works as the frame. Glulam is a poorer fit for a plot where a lorry can't get in and a crane can't stand, and for a tight budget: then a timber house is better built from profiled timber or as a timber frame. An even more factory-made option with wood on the inside, CLT panels, is described on the page about CLT houses.

How much a glulam house costs

The shell of a glulam house costs from 1,980 to 2,400 ₾ per m² of floor area. The price includes the foundations, walls from the factory kit with assembly, floors and the roof. Windows, building services, finishing and the design are priced separately. A turnkey glulam house costs from 3,000 ₾ per m², and finishing starts straight away, with no pause for settling.

Separate items: a glulam wall with materials and installation from 690 ₾ per m² of wall, a foundation slab from 390 ₾ per m² of the house footprint, and thermally broken aluminium windows, installed, from 780 ₾ per m². Profiled timber is cheaper, with a shell from 1,200 ₾ per m², and CLT panels cost more, from 2,220 ₾.

Costs go up with a larger timber section, panoramic glazing, a complex roof and difficult access. They come down with a simple plan with repeating walls and standard-size windows. We send a preliminary estimate from a sketch within 24 hours on business days. The final cost is set on the basis of the design and the factory's shop drawings, after a visit to the plot and once the estimate is agreed.

Stages and timelines

  1. Design and shop drawings

    1–2 months

    The factory breaks the house down into individual timbers, and our structural engineer checks the calculation for seismic loads and the ground. You sign off the shop drawings.

  2. Foundations

    3–5 weeks

    While the factory makes the kit, we pour the slab or ground beam, bring the top of the plinth to level and set the anchors.

  3. Delivery and acceptance

    1–3 days

    We unload the kit by crane, count it against the schedule, measure the moisture and stack it under cover.

  4. Walls and floors

    2–4 weeks

    Walls to the assembly diagram, floor beams, settling frames in the openings and anchoring to the foundations.

  5. Roof and windows

    2–4 weeks

    Rafters, roof covering, gutters, and windows in their settling frames. After this, work can go on inside in any weather.

  6. Finishing

    2–3 months

    Building services, bathrooms on a frame, sanding and coating the walls. We start straight away, with no pause for settling.

Local specifics in Batumi

In Batumi, glulam lives between two regimes. In summer the air conditioning runs in the rooms, so the air indoors is dry and cool while it is humid outside, and the wall sits between the two. In winter the heating dries out the inner side. So on the inside we use vapour-permeable finishes, and in a house that is cooled constantly in summer we include extract ventilation and dehumidification, so that the moisture content of the timber doesn't swing from season to season.

The kit arrives on lorries, and long timbers need access and room for unloading. On the narrow streets of the suburbs a lorry sometimes can't reach the gate, and then the kit is moved onto a smaller vehicle and the crane works an extra day. We check the access before ordering, together with the spot for the crane.

Closer to the sea, salt damages the steel in a timber house faster: hidden brackets, anchors, terrace fixings. These parts are stainless steel or hot-dip galvanised.

Materials and brands

The walls are assembled from softwood glulam, usually spruce or pine, with a 180–200 mm section and a “comb” profile. For external walls we use timber glued with an adhesive for structures exposed to the weather and humidity, and we ask the factory for documents on the adhesive and the gluing. The seal between the courses, the dowels and the fixings are listed in the specification.

Windows for large openings go on thermally broken Asistal aluminium systems, and ordinary ones can be on REHAU profiles. Under tiles in wet areas goes Knauf moisture-resistant plasterboard on its own frame. We match the timber finishes to the factory primer, if there is one.

What makes up the cost

Timeline: a 150 m² glulam shell usually takes 1–2 months after the kit is delivered, and the factory sets the production time

  • what the factory supplies: dowels, fixings, seals

What raises the cost

  • a larger timber section and long glulam beams for the spans
  • panoramic glazing in thermally broken aluminium
  • narrow access, where a lorry can't reach the gate
  • a complex roof and cantilevered canopies

What lowers the cost

  • a simple plan with repeating walls and standard windows
  • finishing straight after assembly: the house doesn't stand empty for a year

We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.

Get an estimate

Guarantees

Our work from foundations to roof carries a 2-year warranty. Wiring, water pipes and drains that we laid in the walls and floors are guaranteed for 5 years. The timber and windows carry the manufacturer's warranty, and we hand over the documents for the adhesive and the gluing with the handover file. Photos of the anchors and of the damp-proofing under the first course also stay in the handover file.

Questions and answers

How much does a glulam house cost in Georgia?

From 1,980 ₾ per m² for the shell: foundations, walls from the factory kit with assembly, floors and roof. Windows, building services and finishing are not included. A turnkey house costs from 3,000 ₾ per m², and the design is priced separately.

What affects the price most is the timber section, the area of glazing and access for the lorry and crane. We send a preliminary estimate from a sketch within 24 hours on business days. The final cost is set on the basis of the design and the factory's shop drawings, after a visit to the plot and once the estimate is agreed.

When can finishing start in a glulam house?

As soon as the house is under its roof and the windows are in. The lamellas are dried before gluing, the wall hardly settles, and there is no pause for settling as there is with profiled timber. Inside, we start with the building services, then move on to sanding and coating the walls, the bathrooms and the floors.

The one thing to hold back on is fierce heating: in the first winter the house is warmed up gradually so that the timber doesn't dry out too much. After the first winter we check the doors and windows, and they usually need only a small adjustment. A house for rent can open to guests in the same season.

Can a glulam house be built to my own design?

Yes. The factory turns any architect's design into shop drawings, and our structural engineer recalculates them for Georgian seismic loads and the ground on your plot. Sometimes the layout is adjusted slightly: wall lengths are matched to the length of the timber, the wall sections next to large windows are widened, and cantilevers are calculated separately.

The sooner the design is reviewed for glulam, the fewer changes there are. If the layout was drawn for a masonry house, we first look at where timber walls will work differently, and only then send it to the factory.

Does a glulam house in Batumi need insulation?

That is for the thermal calculation for your house to decide. Winters in Batumi are mild, and a 200 mm glulam wall by the sea doesn't always need extra insulation. Such a house loses heat mainly through the windows, roof and floor, so these are insulated in any case.

In the mountains of Adjara the wall is more often insulated on the outside, under cladding with a ventilated air gap, and the timber stays visible only inside. We don't insulate glulam on the inside: the wood itself then becomes the cold surface, vapour from the room condenses in it, and behind the lining nobody can see it happening.

Will a glulam house withstand an earthquake?

Glulam walls weigh several times less than masonry ones, and a tremor puts a smaller force on the house. But what makes it earthquake-resistant is the calculation. The structural engineer checks how the walls are connected to each other and to the foundations: anchors through the bottom courses, dowels up the height of the wall, short cross walls notched into long walls.

After the check, the usual additions are anchors at the ends of the walls and narrower openings on the ground floor, or a steel frame next to them. Sometimes it is simpler to give up one large window than to strengthen the wall around it, and we show both options in the estimate. The site foreman photographs the anchors before they are covered, and the photos stay in the handover file.

Further reading

Send us your design or sketch, and we'll check it for glulam and price the shell

We reply within an hour during business hours. Message us or leave a request: we’ll call you back, go over the details and suggest the next step.

Mon–Fri 10:00–19:00, Sat 11:00–16:00

Estimate within one business day

Step 1 of 3
Property type
Current condition
Step 2 of 3
When to start
    Step 3 of 3
    Preferred contact method

    How would you like to reach us?

    We’ll call you back at a time that suits you

    Preferred contact method
    Best time to call

    Search the site