A CLT panel house is assembled by crane from solid timber slabs cut at the factory: the walls, floors and roof arrive ready, with the openings already cut out. In Georgia this is a rarity: we haven't found any CLT production here, so the panels would have to be ordered and shipped from abroad. We do the foundations, the installation and everything after the shell, and before ordering we price glulam and a timber frame alongside it. The shell costs from 2,220 ₾ per m².
from 2 220 ₾/m²foundations, panels with crane installation, roof and windows, excluding facade, utilities and finishing. The final price is confirmed once agreed.
- Timeline: installing a 150 m² CLT shell usually takes 1–3 weeks, but with design, manufacturing and delivery the road to the shell takes several months
- Warranty: Panel installation, foundations and roof carry a 2-year warranty
Who it’s for
You have seen CLT houses in Europe and want to know whether one can be built in Batumi
You have a CLT design from a European architect and need it calculated for Georgian seismic loads
You want timber walls and ceilings with no settling and are ready to pay for factory precision
You need a shell that can be assembled in a few days on prepared foundations
You are choosing between CLT, glulam and a timber frame and want to compare them by estimate
What’s included
- A comparison of CLT with glulam and a timber frame by estimate and timeline before ordering
- A check of the factory's calculation and connections by our structural engineer against Georgian codes
- Agreeing the cutting plan: openings, cable channels, holes for pipes
- A foundation slab with anchors to the factory's diagram
- Preparing the access, the crane pad and the unloading area
- Acceptance of the panels against the schedule and crane installation
- Protecting panel edges and floors from rain, with the roof on straight after installation
- External insulation, membranes and a ventilated facade
- Floating floors on sound insulation between storeys
CLT, or cross-laminated timber, is a panel made of several layers of boards, with each layer laid across the one before it. Once glued under a press, it works as a slab: it carries loads in both directions and, within its own plane, hardly changes size with moisture. Abroad, these panels are used for private houses and multi-storey buildings alike. In Batumi a CLT panel house is still a rarity, and we start any conversation about one with where to get the material.
How a CLT house is assembled
The factory cuts the panels on a CNC machine to the design of the house: it cuts out the windows and doors, the rebates for the joints, the holes for pipes and the channels for cables. The panels arrive on site numbered, and a crane sets them on the foundations according to the assembly diagram. The walls are connected to each other and to the floors with steel angle brackets and long screws, and fixed to the foundations with anchors that hold the wall against sliding and uplift.
A CLT wall in a private house is usually 100–140 mm thick. It carries the load, keeps the house rigid in a tremor and in wind, and can stay as bare wood on the inside. It doesn't hold heat well, so insulation and a facade go on the outside. CLT has almost none of the settling you get with solid timber, and finishing starts straight after installation.
CLT in Georgia: where to get the panels
We haven't found any CLT production in Georgia, and we haven't seen ready-made CLT houses offered on the local market either. That means the panels will have to be ordered from a factory abroad, and we name the factory and the country of supply in the estimate once the choice is made. For a single private house this means a design for a particular factory, a place in its production queue, delivery by lorry or by sea in containers, and customs clearance. Panel size is limited by transport, so long walls and floors are cut into sections, and every extra joint adds work during installation.
We don't suggest ordering CLT straight away. When we get such a request, we price the same layout in two other methods as well and show how much time and money the delivery will take, and you make the decision on the figures. Delivery to Batumi and customs are usually handled by the supplier, and sometimes by a broker you hire. On our side are the factory's lead times before the contract, the site, the crane and accepting the panels against the schedule.
Seismic design: what the factory does and what our structural engineer does
The factory designs the panels and connections to the codes of its own country. For Georgia this isn't enough, and our structural engineer recalculates the house to the Georgian seismic code and the ground conditions of the plot. A CLT house is light and rigid, and in an earthquake everything comes down to the connections: hold-down anchors against uplift at the ends of the walls, angle brackets against sliding, and the connection between the floors and the walls. The structural engineer checks these first, and after the check the connections may change, and a large window may need a solid section of wall next to it.
Our structural engineer's comments go to the factory, and the factory revises the cutting plan. Until the connections are agreed on both sides, the panels don't go into production. What else helps a house withstand a tremor is covered on the page about earthquake-resistant construction.
Crane installation and protection from rain
A CLT shell goes up quickly: the walls and floors of a small house are installed in a few days. For those days you need access for a lorry and a mobile crane, a crane pad on firm, level ground, and space for unloading if the installation can't keep pace with the deliveries. On a slope or a narrow street, preparing the access can cost more than the installation itself.
The panels must not get wet during the build. Water that gets into the edges and joints takes a long time to come out and leaves stains on the visible surface. So we try not to schedule installation in the rainy season, from September to January, and pick dry weeks. We cover the edges and tops of the walls with a membrane straight after installation, tape plastic sheeting over the floors, and put the roof on right after the last panel.
Insulation, facade and vapour
The insulation goes on the outside of the panel: mineral wool as calculated, a breather membrane and a ventilated facade with an air gap. On the inside the wood stays solid, and a vapour barrier membrane like the one in a timber frame house usually isn't needed: the panel itself holds back vapour, and if moisture gets into the wall, it lets it out through the mineral wool and the air gap. The engineer still checks the wall build-up with a moisture calculation, because in Batumi in summer vapour moves from the street into the cool room.
The cladding can be timber boards, fibre cement or porcelain tiles on a subframe. For CLT we recommend a ventilated facade rather than render over insulation: if water ever gets behind the cladding, it has somewhere to go. How else these two solutions differ is explained in our comparison ventilated facade vs ETICS.
Fire and noise between floors
The fire resistance of CLT walls and floors is calculated from the thickness of the panel and the number of layers, and where there isn't enough margin, the panel is covered with plasterboard. The flue of a fireplace goes through the floor in a non-combustible firestop.
Noise is harder to deal with. A CLT floor is light, and footsteps from above can be heard if the floor finish sits directly on the panel. So on top we lay a floating screed or a dry floor on a sound-insulating layer, and underneath, if needed, a suspended ceiling. In a house for rent this is a must, and how to lay out the rooms so that bathrooms, not just a single wall, sit between neighbouring beds is shown on the page about guest houses.
CLT panel house or another method
People choose CLT for the wood in the interior and a fast, precise shell. In Batumi a similar result can be achieved another way, usually for less and with a material that is easier to get:
- glulam gives the same timber wall on the inside and hardly settles, and its shell costs less;
- a timber frame house of kiln-dried timber, lined inside with tongue-and-groove boards or veneer, costs several times less, and the timber for it is sold in Georgia;
- a cast-in-place concrete frame house with wood in the finishes copes better with damp and needs less upkeep;
- a mixed scheme: masonry walls, with CLT only for the floors or the roof, where the wood is visible on the ceiling; far fewer panels are needed then, and the bearing on the masonry is calculated by the structural engineer.
We compare by estimate: the same layout in two or three methods, with the shell price, timeline and upkeep. If CLT still comes out on top after that, we start corresponding with the factory.
How much a CLT panel house costs
The shell of a CLT panel house costs from 2,220 to 2,760 ₾ per m² of floor area, and this covers the foundations, the walls, floors and roof made of factory-cut panels, crane installation, the roof covering and the windows. Unlike our timber and log shells, windows are already included here. Utilities, finishing and the design are priced separately, and a turnkey house starts from 3,420 ₾ per m².
The biggest line in the estimate is the panels: from 570 ₾ per m² of wall or floor, including cutting, delivery and installation. A foundation slab costs from 390 ₾ per square metre of footprint. Insulation and the ventilated facade are not included in the shell: a turnkey ventilated facade with materials starts from 420 ₾ per m² of facade. For comparison, glulam costs from 1,980 ₾ per m² for the shell and from 3,000 ₾ for a turnkey house.
Costs go up with delivery from abroad and the exchange rate, long panels that travel as an oversize load, difficult crane access and a visual-grade surface in every room. They come down with a simple plan and industrial-grade panels wherever the finishes will cover them. We send a preliminary estimate from a sketch within 24 hours on business days, and the final cost is set on the basis of the design and the factory's calculation, after a visit to the plot and once the estimate is agreed.
Stages and timelines
-
Comparison and choice of factory
3–6 weeks
We price CLT alongside other methods, ask factories for lead times and prices, and you choose the option.
-
Design and cutting plan
1–2 months
The factory prepares the cutting plan and calculation, our structural engineer checks them, and after revisions you sign off the cutting plan.
-
Slab and crane pad
3–5 weeks
We pour the slab with anchors and prepare the crane pad while the panels are in production and in transit.
-
Shell installation
1–3 weeks
The crane sets the walls and floors, we cover the edges with membrane straight away and put on the roof.
-
Insulation, facade, windows
4–6 weeks
External insulation, breather membrane, ventilated facade and windows.
-
Building services and finishing
2–3 months
Services run through the channels in the panels, then floating floors and bathrooms on a frame. There is no pause for settling.
Local specifics in Batumi
For CLT in Batumi, logistics count for more than the climate. The panels travel by lorry across several borders or by sea in containers to the port, and the delivery time depends on more than just the factory. We set the installation date once the panels have left the factory, and book the crane for it.
Installation needs dry weather and little wind: a panel on slings catches the wind like a sail, and in a strong wind off the sea the crane won't lift it. In autumn and early winter there are few such days, which is one more reason to schedule installation in the dry months.
By the sea, salt works against steel, and a CLT house has a lot of it: angle brackets, anchors, screws at the joints. External and plinth connectors have to be stainless or hot-dip galvanised, and the internal ones are kept inside the insulated envelope. In the mountains snow comes on top of this, and the thickness of the roof panels is calculated for the snow load on the plot.
Materials and brands
The CLT panels are softwood, usually spruce, 100–140 mm thick for the walls and floors of a private house. We order a visual-grade surface only where the wood will stay exposed, and elsewhere use industrial grade, which the finishes will cover. The factory's documents for the panels and the adhesive come with the delivery.
On the outside go mineral wool, a breather membrane and a ventilated facade: porcelain tiles or composite panels on a subframe, fibre cement or timber boards. Thermally broken aluminium systems, such as Asistal, suit panoramic openings, and VEKA uPVC profiles suit ordinary windows. Knauf plasterboard goes where a panel has to be covered for fire resistance.
What makes up the cost
Timeline: installing a 150 m² CLT shell usually takes 1–3 weeks, but with design, manufacturing and delivery the road to the shell takes several months
- the choice of factory: price, production queue and scope of supply
What raises the cost
- delivery of the panels from abroad and the exchange rate
- a visual-grade panel surface in every room
- long panels that are shipped as an oversize load
- access and a pad for a mobile crane on a slope
What lowers the cost
- a simple plan with repeating panels and standard openings
- finishing straight after installation, with no pause for settling
We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.
Get an estimateGuarantees
Panel installation, foundations and roof carry a 2-year warranty. A 5-year warranty applies to the wiring, water pipes and drains in the walls and floors that we laid. The panels, windows and facade materials carry the manufacturer's warranty. We photograph the connections and anchors before they are covered, and these photos go into the handover file together with the factory's documents.
Questions and answers
How much does it cost to build a CLT panel house?
The shell costs from 2,220 ₾ per m²: foundations, walls, floors and roof made of factory-cut panels, crane installation, the roof covering and windows. A turnkey house costs from 3,420 ₾ per m². Insulation with a ventilated facade, building services, finishing and the design are not included in the price of the shell.
What moves the price most is the delivery of the panels, the exchange rate and crane access. We send a preliminary estimate from a sketch within 24 hours on business days. The final cost is set on the basis of the design and the factory's calculation, after a visit to the plot and once the estimate is agreed.
Are CLT panels made in Georgia?
We haven't found any such production in Georgia. The panels have to be ordered from a factory abroad, and they are made for a specific design: the cutting is done at the factory, so you can't buy CLT off the shelf like boards or blocks.
So the timeline of a CLT house depends on the factory's queue and on delivery, and the price on the exchange rate. Before asking factories for quotes, we price the same layout in glulam and as a timber frame. If CLT wins for what you need, we handle the correspondence with the factory and agree the cutting plan together with you.
How is CLT different from SIP panels?
Both are called panels, but they are built quite differently. A SIP panel has expanded polystyrene sandwiched between two OSB boards: it is light and warm but lets almost no vapour through, and walls made of it are always covered with finishes. CLT is a solid timber slab of several layers of boards with no insulation inside. It is heavier, carries the walls and floors itself, and the insulation goes on the outside.
In price they are far apart: a SIP panel shell costs several times less, while CLT is closer to glulam. In return, the inside of a CLT house can be left as exposed wood.
Does a CLT house burn?
It burns, like any wood, but a thick glued slab behaves differently from the studs of a timber frame. In a fire it chars on the surface, the charred layer slows down the heating of the layers beneath, and the panel carries its load for a long time. How long it will hold is calculated from the thickness and the number of layers, and where there isn't enough margin, the panel is covered with plasterboard.
House fires most often start not with the walls but with the wiring or a stove. So cable inside the panels runs only in protective conduit through the channels cut by the factory, junction boxes stay accessible, and the wall behind a fireplace or stove is covered with a non-combustible shield.
Can CLT walls be left without any finish inside?
Yes, if the panels are ordered with a visual-grade surface: their top layer is made of selected boards without large knots or patches. After installation, these walls and ceilings are sanded at the joints and coated with an interior oil or lacquer. A visual-grade surface costs more, so it is used only where the wood will be on view.
An exposed panel has to be protected on site from rain, dirty boots and marks from the lifting slings. Sockets and switches go into channels cut by the factory, and their positions are agreed before cutting. In bathrooms the panel is covered with a frame for tiles, and in the kitchen with a splashback.
Further reading
Send us your CLT design, and we'll compare it with glulam and a timber frame by estimate
We reply within an hour during business hours. Message us or leave a request: we’ll call you back, go over the details and suggest the next step.
Mon–Fri 10:00–19:00, Sat 11:00–16:00