Energy-efficient houses in Batumi are built for the local climate: here it matters more that the house doesn't overheat in summer or get damp than that it holds its heat in a frost. We insulate the walls, roof and floor with a continuous layer without thermal bridges, fit windows installed within the insulation layer and shaded from the sun, and design ventilation with heat recovery. This specification adds from 270 ₾ per m² to a turnkey house, and the heat pump and solar panels are priced separately.

from 270 ₾/m²extra on a turnkey house: insulation, windows set in the insulation, heat recovery, per m². The final price is confirmed once agreed.

  • Timeline: The design with thermal calculations usually takes 1.5–2 months, and a 150 m² turnkey house another 9–12 months, with the air tightness test before the finishing
  • Warranty: 2 years on the work, 5 years on concealed pipes and wiring
Get an estimate

Who it’s for

  • You're moving to Batumi for good and want a house that is warm in winter, not too hot in summer and free of damp

  • You're building in the Adjara highlands, where the winter is colder and the heating is needed for longer than by the sea

  • The house will stand empty for half the year, and you don't want mould in the corners while you're away

  • You're thinking about a heat pump and solar panels but don't know which of them you actually need

  • You're building a guest house where in summer the air conditioners run in every room at once

What’s included

  • Thermal calculations for the envelope and the insulation thickness
  • Details without thermal bridges: plinth, balcony slabs, lintels, roof junctions
  • Windows installed within the plane of the insulation
  • Sun shading: overhangs, canopies, external blinds, solar control glass
  • Mechanical supply and extract ventilation with heat recovery, design and installation
  • Selection and installation of a heat pump and low-temperature heating
  • Preparing the roof for a solar system, and installing it under a separate estimate
  • An air tightness test and thermal imaging survey before the finishing

Prices: energy-efficient houses

from 270 ₾/m²

WorkPrice
Energy-efficient house specification (extra charge on a turnkey house)270–360 ₾/m²
Turnkey energy-efficient house1 950–2 220 ₾/m²
Mechanical ventilation with heat recovery for a 120–180 m² house17 400–24 000 ₾/pc
Air-to-water heat pump, 12–16 kW, installed14 400–18 000 ₾/pc
Turnkey rooftop solar power system, 5 kW15 600–18 000 ₾/pc
House air tightness test and thermal imaging survey1 020–1 440 ₾/pc
Turnkey ETICS facade, with materials205–250 ₾/m²
uPVC windows, installed330–480 ₾/m²

extra on a turnkey house: insulation, windows set in the insulation, heat recovery, per m². The final price is confirmed once agreed.

An energy-efficient house in Georgia is often pictured along northern lines: thick insulation and all the attention on winter. Energy-efficient houses in Batumi have a different job to do. The winter is mild, while the summer is long, hot and humid, and the house needs cooling and dehumidifying just as much as heating. So we design the envelope and the building services for both seasons: in winter the house holds on to its heat, and in summer it keeps out the sun and the damp.

Energy-efficient houses in Batumi: Georgian law and the Passive House standard

Georgia has a law on the energy efficiency of buildings. It sets minimum energy performance requirements for new buildings, provides for an energy performance certificate and a gradual move to nearly zero-energy buildings. The law has been amended, and it doesn't apply to every building, so we check the requirements for your house with the architect under the rules in force in 2026, as of the date the documents are submitted.

The law doesn't require a passive house. Passive House is a voluntary standard developed by the Passive House Institute in Germany. A house built to it uses very little energy for heating and cooling, its envelope is tested for airtightness, and compliance with the standard is confirmed by an independent certifier.

An envelope without thermal bridges

A thermal bridge forms wherever heat finds a way around the insulation: a balcony slab that runs through to the outside, a lintel over a window, a column within the masonry, the plinth. In Batumi not much heat escapes through these spots, but in winter moisture collects on them. Humid air condenses on the cold concrete, and mould appears in the corner. So we draw each of these details separately in the design:

  • we fit the brackets of a ventilated facade with thermal break pads, otherwise each one carries the cold through the insulation;
  • we separate balcony and terrace slabs from the floor slab with thermal break elements, as the structural engineer calculates, or insulate them on all sides;
  • we insulate the plinth and the ground-bearing slab with extruded polystyrene, which water doesn't harm;
  • we take pipes and cables through the envelope in airtight grommets, so as not to break the vapour barrier;
  • we insulate the roof more thickly than the walls, because in summer that is where most of the sun's heat gets into the house.

The thickness of the layer is calculated by a building physics engineer, and on our walls it is usually 100–150 mm of mineral wool. On the sea-facing side the facade over the insulation is more often ventilated, and in a sheltered spot rendered; there is more on this in our comparison of a ventilated facade and ETICS.

Windows, sun and overheating

A window loses heat not only through the glass but also through the frame and the installation joint. We set the frame forward into the insulation layer, take the insulation over the frame on the outside, and seal the joint with tapes: a vapour barrier tape on the inside and a vapour-permeable one on the outside that keeps out wind-driven rain. In Batumi a double-cavity glazed unit with a low-e coating is usually enough, with solar control as well on south- and west-facing windows. We choose the profile to suit the location: aluminium and uPVC by the sea behave differently.

In summer the main concern is the sun. A large west-facing window that looks great in the concept drawing turns the living room into a greenhouse by July, and the air conditioning runs non-stop. Roof overhangs and canopies over south-facing windows help, as do external blinds or roller shutters on west-facing ones, and solar control glass where shade isn't possible. Curtains inside do little: by then the heat has already come through the glass and stays in the room.

Ventilation with heat recovery, and humidity

An airtight house without ventilation soon gets damp: showers, cooking and breathing produce moisture every day, and it has nowhere to go. So here a mechanical supply and extract ventilation unit runs all the time. Fresh air is supplied to the bedrooms and living room and extracted from the kitchen and bathrooms, and the heat recovery unit between the two airflows passes the warmth of the outgoing air to the fresh air in winter, and its coolness in summer.

For Batumi we usually fit an enthalpy heat recovery unit. It also transfers some of the moisture between the airflows, so in the sticky heat of July the supply air brings less damp into the house. It doesn't fully dry the air: in summer the air conditioners do that job, and between seasons a separate dehumidifier may be needed. We position the unit so that the filters, which are changed several times a year, can be reached without taking the ceiling apart.

Heat pump and solar panels

An airtight house needs little heating capacity, and the simplest way to provide it is an air-to-water heat pump with underfloor heating or fan coil units, which also cools the house in summer. A heat pump costs from 14,400 ₾ installed, and its output is chosen by a heat loss calculation. If there is gas at the edge of the plot, see our comparison of a heat pump vs a gas boiler. The gas pipe is connected by the gas service; we don't touch it.

A 5 kW rooftop solar system costs from 15,600 ₾. Batumi has more overcast days than eastern Georgia, so the same system produces less energy here. On the other hand, peak output in summer comes during the hours when the air conditioners are running. We prepare the roof for the system in advance: the pitch, embedded fixings for the mounting, a place for the inverter and the cable route. Surplus power can be exported to the grid under the microgeneration rules. The way exported energy is paid for at new installations is changing, so we check the terms with the distribution company under the rules in force in 2026, and again before connection.

When energy efficiency pays off

We calculate the savings for your design at current tariffs, and the set of measures depends on how the house will be lived in:

HouseWhat is worth itWhat can wait
A house by the sea lived in all year roundAn envelope without thermal bridges, windows installed within the insulation, sun shading, heat recovery, a heat pumpPassive House certification
A house you visit for the summerRoof insulation, overhangs and external blinds, air conditioners with dehumidificationHeat recovery and thick insulation on the walls
A house in the Adjara highlandsThick insulation, energy-efficient windows, airtightness, a heat pump with backup or a boilerSun shading on every facade
A guest house for rentSun shading, ventilation in the guest rooms, a shared heat pumpThe solar system, though we prepare the roof for it straight away

For a house lived in all year round we design the full set from the start. Energy efficiency is cheapest at the concept stage: the shape of the house, the orientation of the windows and the overhangs cost almost nothing then, while correcting them in a finished house is expensive.

How we check the result

We check airtightness with a test: the house is closed up, a fan in the doorway creates a pressure difference, and an instrument shows how much air leaks through the gaps. We do it before the finishing, while the membranes and joints are still exposed and a gap can be taped up in minutes. On the same visit a thermal imaging camera shows the cold spots around the windows, roof and plinth. Thermal imaging needs a temperature difference, so the survey is best planned for the cooler season. The air tightness test and thermal imaging survey cost from 1,020 ₾.

How much an energy-efficient house in Batumi costs

The energy-efficient specification adds from 270 ₾ per m² to the price of a turnkey house. This extra covers thicker than usual wall and roof insulation, windows installed within the insulation layer, details without thermal bridges, and ventilation with heat recovery. The ventilation makes up a noticeable part of it: a heat recovery system for a 120–180 m² house costs from 17,400 ₾. A turnkey house built to this specification costs from 1,950 ₾ per m², and the heat pump and solar panels are priced as separate lines.

Large south- and west-facing windows, a complex shape with cantilevers and a house in the mountains push the price up. We send a preliminary estimate from the house plan and photos of the plot within 24 hours on business days; the final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.

Stages and timelines

  1. Brief and plot

    1 week

    We look at the orientation of the plot, shade from neighbours and the mountains, how often you will live in the house and whether you need Passive House certification.

  2. Concept designed around the sun

    2–3 weeks

    We orient the windows to the sun, calculate the roof overhangs and canopies, and look for a compact shape without unnecessary projections.

  3. Thermal design and details

    3–5 weeks

    The building physics engineer calculates the insulation thickness, and the structural engineer and architect draw the details for the balconies, plinth, windows and roof.

  4. Building services design

    2–4 weeks

    Ventilation with heat recovery, a heat pump and low-temperature heating, and preparation of the roof for a solar system.

  5. Envelope on site

    1–2 months

    Insulation, membranes and windows installed within the insulation layer. We photograph the details before they are covered.

  6. Test and thermal imaging

    2–3 days

    We test the air tightness before the finishing, tape up any gaps we find and survey the walls with a thermal imaging camera.

  7. Commissioning

    1–2 weeks

    We set the airflow for each room and the heat pump modes, and hand over the instructions and the handover file.

Local specifics in Batumi

Humidity in Batumi is high all year round, and for an energy-efficient house it is the main design factor. An airtight envelope without ventilation gets damp faster here than in a dry climate, and in winter any thermal bridge becomes a wet patch. That is why we design the ventilation and the insulation details before the finishes, and don't simplify them during the build to save money.

The sides of the house behave differently. The south and west facades overheat in summer, while the side facing the sea takes wind-driven rain and salt: we put the heat pump's outdoor unit under cover on the sheltered side, and use corrosion-resistant fixings for the solar panels. We store the insulation under cover and close it in with the facade in dry weather, because wet mineral wool holds heat less well and takes a long time to dry. In the Adjara highlands the winter is colder and snowier, so the insulation layer there is thicker, and the heat pump needs spare capacity for frosty days.

Materials and brands

For the walls and roof we use stone wool: it doesn't burn and lets vapour through. Under the ground-bearing slab and on the plinth we use extruded polystyrene. We choose the membranes and window tapes from a single system rather than separately, otherwise the joints between them don't hold.

Windows are made with REHAU or VEKA uPVC profiles, and large openings in thermally broken Asistal aluminium; these systems are sold in Georgia. Mitsubishi Electric heat pumps are sold in Georgia with installation and servicing, and for a heat pump by the sea servicing matters more than the brand, because the outdoor unit needs regular maintenance. We choose heat recovery units and solar panels by their class, the manufacturer's warranty and whether the seller has a service team in Georgia.

What makes up the cost

Timeline: The design with thermal calculations usually takes 1.5–2 months, and a 150 m² turnkey house another 9–12 months, with the air tightness test before the finishing

  • the heat pump and solar system are priced separately

What raises the cost

  • large south- and west-facing windows that need sun shading
  • a complex house shape with cantilevers, bay windows and projecting slabs
  • a house in the mountains, where the insulation is thicker and the heating needs a backup
  • the aim of passing a test to the Passive House standard

What lowers the cost

  • a compact house with its windows oriented to the sun at the concept stage
  • a simple roof without valleys or roof windows

We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.

Get an estimate

Guarantees

We photograph membranes and window joints before they are covered.

We give a 2-year warranty on the work, including the ventilation and the underfloor heating and heating pipes. Water pipes, drains and wiring in walls and floors carry a 5-year warranty if we installed them. The heat pump, heat recovery unit, panels and inverter are covered by the manufacturer's warranty, and we hand over the documents for them in the handover file.

Questions and answers

How much does it cost to build an energy-efficient house in Batumi?

A turnkey house built to an energy-efficient specification costs from 1,950 ₾ per m². Compared with an ordinary house, the extra is from 270 ₾ per m²: it covers thicker wall and roof insulation, windows installed within the insulation layer, details without thermal bridges and ventilation with heat recovery.

A heat pump, from 14,400 ₾ installed, and a 5 kW solar system, from 15,600 ₾, are separate lines. We send a preliminary estimate from the plan within 24 hours on business days; the final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.

Do you need a passive house in Batumi's mild climate?

A certified passive house is rarely needed here. Batumi needs little heating, and the last few centimetres of insulation and the strict airtightness requirements that certification calls for achieve less here than in Central Europe, where the standard was developed.

The principles of the passive house still work here: continuous insulation, an airtight envelope, ventilation with heat recovery and sun shading. That is how we build, and we check the result with an air tightness test. If you do want certification, we build its requirements into the design from the first sketch, and the assessment is carried out by an independent certifier.

Are solar panels worth it on a house in Adjara?

If the house is lived in all the time, has a heat pump and air conditioners running, and the roof has a slope facing south, east or west with no shade from the mountains or neighbouring houses, a system usually makes sense. For a house you visit for a couple of summer months the benefit is much smaller: for most of the year the system is powering an empty house.

We calculate the output from the orientation and pitch of your roof and compare it with the house's consumption. A 5 kW system costs from 15,600 ₾, and it doesn't have to go in straight away: it can be added a year or two after the house is handed over.

Won't an airtight house be damp?

It is an airtight house without ventilation that gets damp, not an airtight house with it. The windows and walls of an energy-efficient house let almost no air through, so the moisture from showers, cooking and breathing leaves only through the extract. The unit runs around the clock at low speed, and in the bathroom and kitchen the speed goes up on a humidity sensor or at the press of a button.

You mustn't switch the ventilation off when you leave for the winter: an empty house without air exchange gets damp just like an occupied one. The unit uses little electricity, and you can monitor it remotely if a communication module is fitted during installation.

Can a house built of aerated concrete or brick be made energy-efficient?

Yes, energy efficiency isn't tied to the wall material. Aerated concrete is warm in itself, but the columns and slabs of a concrete frame in such a wall are cold, and without continuous insulation on the outside heat escapes through them and moisture collects. Solid brick holds heat much less well than aerated concrete, so it needs a thicker layer of insulation.

Timber frame and light gauge steel (LGS) houses are insulated inside the wall, and there what matters most is a well-sealed vapour barrier and a continuous layer outside the frame. Whichever the option, the building physics engineer calculates the thickness and the details, and an air tightness test checks the result.

Further reading

Send us the house plan and the plot location on a map, and we'll price the extra for energy efficiency

We reply within an hour during business hours. Message us or leave a request: we’ll call you back, go over the details and suggest the next step.

Mon–Fri 10:00–19:00, Sat 11:00–16:00

Estimate within one business day

Step 1 of 3
Property type
Current condition
Step 2 of 3
When to start
    Step 3 of 3
    Preferred contact method

    How would you like to reach us?

    We’ll call you back at a time that suits you

    Preferred contact method
    Best time to call

    Search the site