Independent construction assessment in Batumi: defects, quantities, design and estimate
An independent construction assessment in Batumi answers a specific question: why there are cracks and leaks, whether the paid-for work was done, whether the house can be built from this design and whether the estimate is fair. We inspect, measure, open up details, find causes with instruments and write a report with photos, references to the contract and standards, and a way to fix it. Defect assessment from 1 980 ₾.
from 1 980 ₾/projectdefect assessment with a written report. The final price is confirmed once agreed.
- Timeline: an assessment usually takes 1–2 weeks from inspection to report, an urgent one is faster
- Warranty: We stand behind the conclusions in our report
Who it’s for
Cracks, leaks or damp have appeared and it is unclear who is at fault
The contractor has issued a record and the quantities look doubtful
You are in a dispute with a developer about an apartment or house
You have a design and want to check it before building
You are comparing estimates and suspect missing work
What’s included
- review of the contract, design, estimate and records
- inspection, measurements and photos
- opening up and concrete testing if needed
- finding causes with a moisture meter and thermal camera
- checking quantities against the design and estimate
- a written report with conclusions
- a way to fix the problems with a rough cost
Independent construction assessment in Batumi: when it is needed and what it gives
An independent construction assessment in Batumi is needed when verbal comments are no longer enough. The screed has cracked, the terrace leaks, the contractor has invoiced quantities you never saw, the developer says the damp in the apartment is "from the occupants". The expert comes, inspects, measures, opens up details if needed and writes a report: what is wrong, why, whose fault it is and how to fix it. With such a document the conversation with the contractor or developer goes differently.
Types of assessment
| Type | Question | Result |
|---|---|---|
| Defects | Why cracks, leaks, damp | Causes, who is at fault, how to fix |
| Quantities and quality | Was the paid-for work done | A reconciliation against the design and estimate |
| Design | Can the house be built from these drawings | Comments on structure and services |
| Estimate | Are the quantities and prices fair | A check against the design and the market |
An assessment answers a specific question about a piece of work or a document. If you need to understand the overall condition of a building before buying it or adding a storey, that is an inspection; more on the building inspection page.
How an assessment goes
- we review the contract, design, estimate, records and correspondence;
- we inspect the property, measure and take photos;
- if needed, we open up details and test the concrete;
- we look for the causes of defects with instruments;
- we write a report with conclusions and ways to fix the problems.
We look for leaks and damp with a moisture meter and a thermal camera, and sometimes with a flood test: that shows where the water comes from, not just where it appears. How waterproofing should be done is on the waterproofing page.
What the report contains
We write the report so that the owner, the contractor and a lawyer can all understand it. It contains a description of the property and the question, a list of defects with photos and measurements, the causes, references to the design, contract and standards, an assessment of who should fix what, and the way to fix it with a rough cost. If there are several parties, we invite them to the inspection so nobody can later say the expert looked without them.
Reviewing the design and the estimate
The best time for an assessment is before construction. We check whether the design has all the sections it needs, whether architecture, structure and services agree, and whether seismic loads and soils are accounted for. In the estimate we check quantities against the design and prices against the market, and look for missing work that would later surface as extra charges. How we prepare and check estimates is on the cost estimates page.
Disputes with a developer
In new builds the most common disputes are about damp, cracks in finishes, windows and ventilation. A report helps you understand what the developer must fix under the contract and demand it in writing. If the defects are minor and quicker to fix yourself, see the fixing a developer's renovation page.
How much an assessment costs
A defect assessment with a written report costs from 1 980 ₾. A check of the volume and quality of a contractor's work with a record from 1 200 ₾, a review of a house design before construction from 1 440 ₾, an independent audit of a contractor's estimate from 4 ₾ per m². A damp survey with a moisture meter and thermal camera from 570 ₾, an airtightness test with thermal imaging from 1 020 ₾, a concrete strength test from 120 ₾ per area. The final cost is set after reviewing the documents and agreeing the scope of the check.
Stages and timelines
-
Question
1 day
What exactly needs to be found out.
-
Documents
1–3 days
Contract, design, estimate, records.
-
Inspection
1–2 days
Measurements, instruments, opening up.
-
Analysis
3–7 days
Causes, standards, who is at fault.
-
Report
1–2 days
Document, photos, review with you.
Local specifics in Batumi
In Batumi's humid climate many defects look the same: stains on a wall can come from a leak, from condensation or from wet concrete that did not dry before the finishes. Humidity rarely drops below 70 %, and the summer dew point can exceed +20 °C, so without measurements it is easy to blame the wrong party. We find the cause with instruments and only then write who should fix it.
Many houses on the coast were built quickly, and contracts with builders often have neither a design nor a proper estimate. In that case the assessment relies on standards and on what was actually built, and the report becomes the basis for a new contract for the repairs.
Materials and brands
A moisture meter, a thermal camera, a hygrometer and humidity loggers, a rebar detector, a rebound hammer, a laser level and distance meter, feeler gauges and crack gauges, an endoscope for cavities, tools for opening up. Concrete cores for laboratory tests when the exact strength is needed. Photos and video linked to gridlines and rooms. The report electronically and on paper, signed by the engineer.
What makes up the cost
Timeline: an assessment usually takes 1–2 weeks from inspection to report, an urgent one is faster
- number of questions and checks
What raises the cost
- many defects and rooms
- opening up and laboratory tests
- a dispute between several parties
- no design and no estimate
What lowers the cost
- one defect with a clear cause
- a full set of documents
We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.
Get an estimateGuarantees
We stand behind the conclusions in our report. If the cause of a defect turns out to be different from what we stated, we inspect again and rewrite the report at our own expense. All photos, measurements and documents from the assessment stay with you.
Questions and answers
How much does a construction assessment in Batumi cost?
A defect assessment with a report costs from 1 980 ₾, a check of a contractor's work volume and quality from 1 200 ₾, a design review from 1 440 ₾, an estimate audit from 4 ₾ per m². The final cost is set after reviewing the documents and agreeing the scope of the check.
Can the report be used in court?
Our report with photos and measurements helps reach agreement with a contractor or developer and serves as evidence for your lawyer. A court may appoint its own expert, and then our materials help that assessment. If the case is heading to court, we discuss with your lawyer in advance what the report needs to contain.
Should the contractor be invited to the inspection?
Preferably. When the contractor is present, they see the same measurements and opening up, and it is harder for them to dispute the conclusions. We send the invitation in writing. If the contractor does not come, we note this in the report and inspect without them. The same applies to the developer and the management company if the defect affects common parts of the building: the roof, the facade or the risers.
How do you tell whether damp is a leak or condensation?
By measuring. A moisture meter shows where the wall is wetter, a thermal camera finds cold zones and thermal bridges, and loggers record air humidity over several days. If water comes from outside, a flood test helps. Only then is it clear who should fix it: the builders, the roofers or the ventilation.
Why review the design before construction?
A mistake in the design is cheapest to fix on paper. We check whether the design has all its sections, whether architecture, structure and services agree, and whether seismic loads and soil are accounted for. We often find missing details and work that is not in the estimate, which would otherwise have surfaced as extra charges.
Further reading
Describe the problem and send photos and documents: we will tell you which assessment you need within 24 hours
We reply within an hour during business hours. Message us or leave a request: we’ll call you back, go over the details and suggest the next step.
Mon–Fri 10:00–19:00, Sat 11:00–16:00