Industrial building construction in Batumi: production workshops

Industrial building construction in Batumi starts with the process: what equipment will be installed, how much it weighs and how much power it draws, and where a crane and extraction are needed. From this we design the frame, the floor and the power supply. A turnkey workshop on a steel frame with sandwich panels, power wiring, work area ventilation and staff facilities costs from 1,200 ₾ per m², with process equipment and the overhead crane priced separately.

from 1 200 ₾/m²turnkey workshop: frame, panels, floor, power wiring, ventilation, staff facilities. The final price is confirmed once agreed.

  • Timeline: a workshop of about 1,500 m² with an overhead crane usually takes 4–6 months on site, plus 3–5 months for the design, power supply and permit
  • Warranty: Building and installation work has a 2-year warranty
Get an estimate

Who it’s for

  • Your furniture or joinery business has outgrown its garage and is moving into a workshop of its own

  • Your food business needs a production building with washable floors and separate clean areas

  • Your steel fabrication shop needs a span for an overhead crane and power for welding

  • You are an investor building a workshop to let and don't yet know what kind of production will move in

  • Your company from Turkey or Europe is setting up production in Adjara and running the project remotely

What’s included

  • a review of the process and the equipment list together with the machine supplier
  • a concept sketch with the flows of raw materials, products and people, and a site plan with a place for a substation
  • a design with frame calculations for the crane and the floor loads
  • column foundations and separate foundations for heavy machines
  • steel frame, sandwich panels, an industrial or epoxy floor
  • power wiring by area, cable trays, distribution boards, emergency lighting
  • work area ventilation and local exhaust at the sources
  • a staff block: changing rooms, showers, toilets, a room to eat in
  • an overhead crane with runway, installed and tested by the manufacturer, as a separate line

Prices: production workshops

from 1 200 ₾/m²

WorkPrice
Turnkey production building or workshop: steel frame, sandwich panels, floor, power wiring, ventilation1 200–1 560 ₾/m²
Steel frame warehouse or hangar shell with sandwich panels (frame, walls, roof, column foundations)580–780 ₾/m²
Overhead travelling crane, 3–5 t, with runway beams, installed51 000–72 000 ₾/pc
Turnkey industrial concrete floor with dry-shake topping115–145 ₾/m²
Epoxy self-levelling floor115–155 ₾/m²
Commercial premises electrical installation, with materials (excluding light fittings)130–180 ₾/m²
Supply and extract ventilation for commercial premises (equipment + installation)205–300 ₾/m²
Sectional door with automatic opener7 200–9 600 ₾/pc

turnkey workshop: frame, panels, floor, power wiring, ventilation, staff facilities. The final price is confirmed once agreed.

A workshop is designed around the process

We start industrial building construction in Batumi with the equipment list: dimensions, weight, power, water, compressed air and extraction for each machine. Alongside it we need a flow diagram: where raw materials arrive, where they are processed, where finished products are stored and where they leave from. From this diagram we position the doors, aisles and work areas, so that a forklift carrying raw materials doesn't cross the workers' route to the changing rooms.

The machine supplier usually provides installation drawings with loads and embedded parts, and we ask for them before the design. We plan the raw materials store at the workshop the same way as a stand-alone warehouse: height for racking, doors, a floor for forklifts.

Floor loads and machine foundations

We design the floor slab for the heaviest thing that will drive or stand on it: machine feet, racks of steel stock, a loaded forklift. Presses, compressors, sawmill machinery and other equipment that vibrates go on their own foundations, separated from the slab by a joint. Otherwise the vibration spreads through the floor, the slab cracks around the machine, and precision equipment nearby drifts out of calibration.

We choose the floor finish to suit the type of production. In a machine shop or a joinery shop, concrete with a hardened surface does the job; in food production, and wherever the floor is washed often, a seamless epoxy resin floor. Ducts for cables and pipes to the machines are built into the slab before the concrete is poured, and spare sleeves go wherever equipment might be moved later.

Overhead crane: decide before the steel is ordered

A crane changes the whole frame. A top-running crane travels on runway beams carried on column brackets, and the columns under it are heavier. An underslung crane hangs from tracks under the trusses, and then the roof structure takes the load. The frame of a workshop is almost always steel, and the general decisions about it are collected on the page about steel-framed buildings. A workshop adds the crane to them: we need to know its lifting capacity, span and hook height before the steelwork drawings are made. The span of the workshop often sets the class of structure as well. Guide figures for the classes are collected on the page about commercial buildings, and we determine the class itself with an architect.

The structural engineer designs the frame for crane braking, impacts and seismic loads together, and how a building is designed for earthquakes is explained on the page about earthquake-resistant construction. We order the overhead crane with its runway from the manufacturer, together with installation and testing, and it is a separate line in the estimate. The brackets on the columns and the crane power supply line are built into the frame and the workshop electrics.

Electrical capacity and the supply connection

We calculate the workshop's power demand from the equipment list with a diversity factor: machines rarely all run at full load at the same time. To that we add lighting, ventilation, the compressor, air conditioning in the staff rooms and spare capacity for new equipment. We take this figure to the network company at the concept stage: if the local grid falls short, a large workshop may need its own transformer substation, and its location has to go onto the site plan straight away.

We split the distribution boards by area of the workshop, so that repairs in one area don't stop the others. Where there are many motors, we include power factor correction, otherwise extra current loads the cables and the transformer.

Ventilation of work areas and heat under the roof

General ventilation can't cope when a pollutant is released at one point. We fit welding stations, grinding and machines that produce wood dust with local exhaust at the source, and size the supply air to make up for the air extracted. Without supply air, outside air is drawn in through the doors and gates, and the extraction runs at half its capacity.

In summer it gets hot under a steel roof and around the equipment, and cooling the whole volume is expensive. So we deliver fresh air directly to the workstations, while warm air leaves through extract units in the roof. The paint area and the flammable liquids store are separated into compartments with their own extraction and walls of mineral wool panels.

Staff facilities and fire safety

Workers need changing rooms, showers, toilets and a room to eat in, and the supervisor needs a small office. We group these in a block by the entrance or on a mezzanine, so that the wet areas stay out of the production hall. Escape routes, exits, the fire alarm and external firefighting water are in the design from the very start, and the requirements for them grow if the workshop handles flammable materials or gas. Gas to the equipment is connected by the gas company: we don't touch the gas pipe, and we leave space for the gas connection according to its conditions.

How much industrial building construction costs in Batumi

A turnkey workshop costs from 1,200 to 1,560 ₾ per m². The price includes the steel frame, sandwich panel walls and roof, an industrial floor designed for the loads, power wiring, work area ventilation and staff facilities. Process equipment, the overhead crane and the design are not included in this price, and the fee for connecting the power is charged by the network company.

An overhead travelling crane of 3–5 t with runway beams and installation costs from 51,000 to 72,000 ₾, and an epoxy floor for food areas from 115 ₾ per m². Mechanical supply and extract ventilation as a separate order costs from 205 ₾ per m², and electrical installation with materials, excluding light fittings, from 130 ₾ per m². A top-running crane, a substation, local exhaust and food-grade clean areas push the price up, while light production without a crane and with staff facilities on a mezzanine brings it down. We send a preliminary estimate from the equipment list and a plan of the plot within 24 hours on business days. The final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.

Stages and timelines

  1. Process brief

    1–3 weeks

    We get the equipment list, loads, power demand and flow diagram from you and the supplier.

  2. Design and power application

    2–3 months

    Site plan, frame with the crane, floors, electrics, ventilation, fire compartments. We submit the application to the network company.

  3. Permit and steel order

    1–2 months

    We submit the documents for the class of structure; after the permit, the fabricator makes the frame and the crane runway beams.

  4. Foundations and frame

    2–3 months

    Foundations for the columns and machines, erection of the frame and crane runways, walls and roof.

  5. Floor and services

    1–2 months

    The slab with cable ducts, power wiring, ventilation, the staff block.

  6. Start-up

    2–4 weeks

    Crane installation and testing, checks of the ventilation and distribution boards, the completion certificate and a handover file with routing diagrams.

Local specifics in Batumi

Industrial plots around Batumi are often in areas where the grid was built for housing. The spare capacity at the substation may not be enough even for a small workshop, and reinforcing the grid takes months. That is why we request the power before we submit the permit documents.

Equipment from Turkey and Europe arrives by sea through the port of Batumi or by road through Sarpi, and large machines have to be brought in before the last wall is closed. We leave an installation opening or wide doors for them and match the construction schedule to the delivery date.

Humid air affects production itself. Timber and cardboard absorb moisture, and in an unheated hall condensation forms on machines with electronics in the mornings, so we separate the raw materials store and the area with sensitive equipment and keep them dry. The structural engineer calculates the seismic load together with the crane and the heavy equipment on mezzanines.

Materials and brands

The frame and the crane runway beams are fabricated in a factory to our drawings; the steel arrives primed, with bolted site connections. The walls and roof are clad in sandwich panels: only mineral wool panels in fire walls and next to hot processes, and elsewhere as the design specifies. The floor is concrete with dry-shake topping, and in food and clean areas we use Mapei epoxy systems.

Power distribution boards are built with ABB or Schneider Electric equipment, and on open cable trays we run flame-retardant cable. The staff rooms and office are cooled by Midea, Gree or LG split systems, and for a large office at the workshop Daikin or Mitsubishi Electric systems are a good fit. We select the ventilation units and the crane by the capacity and lifting capacity in their data sheets, and agree the brand with you.

What makes up the cost

Timeline: a workshop of about 1,500 m² with an overhead crane usually takes 4–6 months on site, plus 3–5 months for the design, power supply and permit

  • span and height matched to the equipment

What raises the cost

  • a top-running overhead crane and heavier columns to carry it
  • your own transformer substation if grid capacity is short
  • local exhaust, a paint area, clean areas
  • separate foundations for heavy and vibrating machines
  • an epoxy floor for food production

What lowers the cost

  • light production without a crane or heavy machines
  • a staff block on a mezzanine inside the workshop

We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.

Get an estimate

Guarantees

Building and installation work has a 2-year warranty. Cables in the floors and walls, and the water pipes and drains of the staff block, if we laid them, have a 5-year warranty. The crane, ventilation units and switchgear come with the manufacturer's warranty, and the routing diagrams and photos of concealed work stay with you in the handover file.

Questions and answers

How much does it cost to build a production workshop in Batumi?

A turnkey workshop on a steel frame with sandwich panels costs from 1,200 to 1,560 ₾ per m². This price includes the frame, the walls and roof, an industrial floor designed for the loads, power wiring, work area ventilation and staff facilities. Equipment, the overhead crane, the design and the power connection are priced separately. The shell of the same building without the floor and services costs from 580 ₾ per m².

The crane, the power supply and the ventilation move the price the most: a joinery shop with local exhaust and an assembly workshop of the same size differ noticeably. We send a preliminary estimate from the equipment list within 24 hours on business days. The final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.

Can an overhead crane be installed in an existing workshop?

Yes, but first the structural engineer checks the frame from the drawings or a measured survey. If the columns and trusses weren't designed for a crane, an underslung crane isn't hung from the trusses, and a top-running crane is put on a separate gantry with its own columns and foundations along the workshop. The floor is opened up for the gantry foundations, and part of the workshop stops work for that time.

This costs more than a crane planned into the design. So if a crane may be needed in a few years, ask us to design the frame for it from the start and leave brackets on the columns: it takes a little more steel, and there will be no alterations later.

How do you get electrical capacity for a workshop in Adjara?

The application to the network company is submitted by the plot owner or by one of our staff under a power of attorney. It needs the plot documents and a load calculation, which we prepare from the equipment list with spare capacity for growth. The network company sets out the conditions, the timeline and the connection fee in its reply to the application, and this fee is not included in our estimate.

Temporary power is a separate matter: the construction site needs electricity before the permanent connection is ready. If a temporary connection can't be obtained, the site runs on a generator, and that is also a line in the estimate. The earlier the application goes in, the fewer months the site spends on a generator.

Can a workshop be built next to houses?

The zoning rules decide: what can be located on the plot is shown in the registry extract and the zoning documents, and we check this before you buy the land. Light production and workshops are allowed in different places from noisy, dusty factories, and the rules differ from zone to zone.

Even if a workshop is allowed, the neighbours will hear the machines and lorries. We put compressors and extract outlets on the side furthest from the houses, turn the doors away from homes, and build the walls around noisy areas with mineral wool. Night work is best discussed before the design: the soundproofing and the position of the building depend on it.

Can a workshop be built in phases?

Yes, and for a business that grows step by step it is a common approach. The first phase gets a few bays of the frame, the staff block and a power connection sized for the whole future floor area at once. We design the frame so that new bays continue the old ones, and make the gable wall removable, from panels on bolts.

We also leave room in the site plan: space to extend the building, separation distances to the neighbours, a route around the building. Each phase goes through its own documents and acceptance, and we build the second phase so that the first keeps working, screened from the dust by a temporary wall.

Further reading

Send the equipment list and a plan of the plot: we'll price the workshop in 24 hours

We reply within an hour during business hours. Message us or leave a request: we’ll call you back, go over the details and suggest the next step.

Mon–Fri 10:00–19:00, Sat 11:00–16:00

Estimate within one business day

Step 1 of 3
Property type
Current condition
Step 2 of 3
When to start
    Step 3 of 3
    Preferred contact method

    How would you like to reach us?

    We’ll call you back at a time that suits you

    Preferred contact method
    Best time to call

    Search the site