Prefabricated timber frame house in Batumi from factory-made panels
A prefabricated timber frame house is assembled on the plot from walls and floors made in a workshop to your design: studs of dry timber and sheathing, and in closed panels the insulation is already in place too. On site the walls and floors go up in a few days, so they spend almost no time in the rain. In return, the design has to be finished before the panels are ordered, the foundations have to be more accurate, and the plot needs access for a crane. It suits guest cabins, a country house and a mountain home. The shell costs from 690 ₾ per m².
from 690 ₾/m²shell of factory-made panels with foundations, roof, windows and assembly. The final price is confirmed once agreed.
- Timeline: the shell of a 100–120 m² prefabricated timber frame house usually takes 2–3 months from ordering the panels, of which installation on the plot takes 1–2 weeks
- Warranty: Panel installation, joints
Who it’s for
Several identical guest cabins on one plot, built to one design
A mountain plot where the dry season is short and the shell has to go up in days
The design is final, and you don't plan to change the layout during the build
A country or summer house, where the price of the shell and a quick start matter
You live far away and want the walls assembled under a workshop roof, not in the rain
What’s included
- Checking the design for factory panels and a seismic calculation of the connections
- Choosing a manufacturer and checking their drawings against our design
- Foundations with the top set level and anchors placed to the panel layout
- Receiving the kit on the plot: markings, moisture, damage
- Installing the wall and floor panels with a crane truck
- Sealing the joints: mineral wool, tape on the breather membrane, a taped vapour barrier
- Roof, gutters and windows, if they are not already in the panels
- Photos of the joints and anchors before they are covered, for the handover file
A prefabricated timber frame house is built from the same studs, insulation and sheathing as an ordinary timber frame house, except that the walls and floors arrive on the plot as ready-made panels. They are made in a workshop to the design, and on site they are set on the foundations, tied together and closed in with the roof. In Batumi this sequence has an obvious advantage: the layers of the wall most sensitive to water are assembled under the workshop roof, not in the autumn rain.
How building with panels differs from framing on site
In an ordinary timber frame house, carpenters cut the timber to fit and build the house wall by wall, and a small design error can be put right on site. With panels the work is split differently: almost everything is decided in the drawings, and the plot is only for installation.
| What we compare | Frame built on site | Factory-made panels |
|---|---|---|
| Where the wall is assembled | On the foundations, in the open | In the workshop; on the plot it is only installed |
| When the final design is needed | Before the timber is bought; small changes are made on site | Before the panels are ordered; after that, a change means a new panel |
| How long the walls stand open | Several weeks | Usually a few days |
| Machinery on the plot | A small lorry is enough | A crane truck and access to the house footprint |
| Weak point | The quality of assembly on site | The joints between panels |
Panels can be open or closed. In an open panel the workshop builds the frame with the external sheathing, and the insulation and vapour barrier are added on the plot. In a closed panel the whole wall is finished, sometimes with the windows in: installation is faster, but you will only see what is inside on the photos from the workshop. How the wall itself is built, and why in Batumi the vapour barrier is chosen with air conditioning in mind, we explain on the page about timber frame houses built on site.
The design and the panel order
The architect divides the house into panels so that they can be delivered and lifted, and so that the joints don't fall at the corners of windows. Before the order, the design has to show every opening, the water and drainage entries, the cable channels, the fixings for the kitchen and the water heater, and the opening for the flue. Once the workshop has cut the timber, moving a window by half a metre means a new panel and another week of waiting.
We don't have our own production: we order the panels from a manufacturer to our design. We check the manufacturer's working drawings against the architectural design and the structural engineer's calculation before they go into production. We also look separately at what timber the manufacturer uses for the frame and at what moisture content, what insulation goes in and how the panels are fixed to one another.
Foundations for panels: accurate to the millimetre
A frame built from timber on site can be adjusted to fit; a panel can't. If the top of the ground beams or slab varies in height, the panel joints open up, the windows go in out of square and the roof lies in waves. So we bring the top of the foundations dead level with a surveyor's level, check the diagonals of the footprint, and set the anchors for the sole plate using a template taken from the panel layout.
As with any light house, we choose the type of foundation from the ground survey: a slab on level ground, piles with ground beams on a slope. The sole plate goes on a damp-proof course and is raised above the ground, and the floor panels over the crawl space are covered underneath with mesh against rodents.
Delivering and installing panels in Batumi
The size of a panel is set not only by the drawings but also by the road. A long panel has to get along the street, turn at the gate and get onto the plot. The crane truck needs a level standing area next to the house, with no overhead wires above it. In tightly built-up streets and on a steep slope we make the panels smaller, and some of them are put up by hand.
The panels arrive in the order of installation and go straight into place, without being stacked on the ground. A small house is taken up to roof level in a few days, so we schedule installation for a window of dry weather and close up the joints the same day. For mountain plots this is the main argument for panels: how delivery and the building season work in the mountains is covered on the page about mountain houses in Adjara.
Joints: moisture, heat and vapour
In the workshop the wall is built true and dry; the weak points appear where the panels meet. Heat escapes through a joint if a void is left in it, and water gets in if the breather membrane of one panel doesn't overlap the next. So we close every joint in the same order:
- we fill the joint cavity tightly with mineral wool;
- on the outside, we lap the breather membranes of neighbouring panels over each other and tape them;
- on the inside, we continue the vapour barrier across the joint and tape it, at the floor and ceiling too;
- we photograph the corners and the junctions with the floors before the inner lining goes on.
We fit the facade on battens with a ventilated air gap on site, over the taped breather membrane, so that the cladding runs continuously and doesn't follow the joints between panels.
Panels filled with mineral wool behave like an ordinary timber frame in humid conditions, not like a SIP panel with expanded polystyrene. How these walls differ in a humid climate is shown in the comparison of SIP panels and timber frame.
Seismic design and fire safety
An earthquake puts only a small force on a light panel house, but all of it passes through the connections: the house is assembled from flat panels, and what holds it together are the ties between them. Panel to panel, panel to floor, sole plate to foundations: the structural engineer calculates every connection to Georgian codes for the ground on your plot. A manufacturer's standard details may be designed for a region without earthquakes, so we don't accept them without a check. A floor made of panels has to work as a rigid diaphragm, and the floor panels are tied together along the full length of each joint.
Fire is held back by the same layers as in a timber frame: the mineral wool inside the panel and the plasterboard that lines the panels on the inside, fitted on site. The workshop makes the cable channels to our wiring layout, and the cables run in them in protective conduit. Exposed timber in the loft and the rafters gets a fire-retardant treatment.
Where a panel house makes sense
Panels pay off most where the design is repeated. Several identical guest cabins on one plot are built from one set of drawings, and each one goes up faster than the one before. What a rental property needs, from a bathroom in every room to quiet between rooms, is described on the page about guest houses. Panels also suit a country house and a mountain plot with a short dry season.
They are a poorer fit for a house of complex shape that you would like to change as the build goes on, and for a plot where a crane can't get in. If you want an even higher degree of factory completion, with finishes and plumbing, that is a modular house.
How much a prefabricated timber frame house costs
The shell of a prefabricated timber frame house costs from 690 to 840 ₾ per m² of floor area. The price covers the foundations, walls and floors made of ready-made insulated panels, the roof, windows and assembly on site. Building services and finishing are priced as later stages, and the design separately as well. A turnkey house costs from 1,470 ₾ per m².
For comparison, the shell of a timber frame house built from timber on site starts from 750 ₾ per m², and a SIP panel shell from 780 ₾. If you have ordered a panel kit yourself, assembly on ready foundations costs from 125 ₾ per m² of the house floor area, labour only. A screw pile with a head plate for a small house costs from 300 ₾ each.
Costs go up with panels from abroad, which bring delivery and customs clearance, with tight access, where the panels have to be made smaller, and with any changes after the order. They come down with a series of identical houses, a simple rectangular plan and a level plot by the road. We send a preliminary estimate from the plan within 24 hours on business days; the final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.
Stages and timelines
-
Design for panels
3–5 weeks
The architect divides the house into panels, and the structural engineer calculates the connections for seismic loads. Openings, service entries and embedded fixings are fixed before the order.
-
Making the kit
3–6 weeks
The manufacturer builds the panels to the checked drawings and sends a photo of each panel before it is closed.
-
Level foundations
2–4 weeks
A slab or piles with ground beams, built while the panels are being made. The top is set level, and the anchors are placed using a template.
-
Delivery and installation
1–2 weeks
The panels arrive in the order of installation, the crane puts up the walls and floors, and we close the joints the same day.
-
Roof and windows
2–3 weeks
Rafters or roof panels, the roof covering, gutters and windows. After this the house is closed against the rain.
-
Final touches and shell handover
1–2 weeks
We tape the joints on the inside, check the membrane throughout the house and sign the completion certificate for the shell.
Local specifics in Batumi
The main constraint for panels in Batumi is access. In the old districts of the city, in Gonio and in Kvariati the streets are narrow, there is little room to turn at the gate, and wires hang over the road. So we decide on the panel length and the crane position after a visit to the plot, not from a map.
On the slopes of Makhinjauri and Chakvi the crane truck needs a level standing area at the level of the house or above it. Sometimes it is easier to build one up with fill for the duration of the installation than to make the panels smaller.
From September to January the rain comes in spells of several days, so we schedule installation for a dry window in the forecast: open joints must not meet a downpour. In mountain Adjara panels are delivered from late spring to autumn, while the roads are passable for a long lorry, and the roof is designed for the snow on the plot.
Materials and brands
The panels are made from planed, kiln-dried timber treated with preservative, sheathed with OSB/3 or a wind barrier board and filled with mineral wool. We order the kit from a manufacturer of timber frame houses. There are such manufacturers in Georgia too, and if the panels come from abroad, delivery and customs clearance are added to the schedule. We ask the manufacturer for the moisture content of the timber, the type and density of the insulation, and the details for fixing the panels together.
The Knauf plasterboard inner lining is fitted on site, once the joints have been taped. Windows are fitted in the workshop or on site, and the profile is chosen to the design: REHAU or VEKA uPVC for ordinary openings, Asistal aluminium for large ones. Fixings on the outside and in the plinth are stainless steel.
What makes up the cost
Timeline: the shell of a 100–120 m² prefabricated timber frame house usually takes 2–3 months from ordering the panels, of which installation on the plot takes 1–2 weeks
- panel type: closed panels cost more in the workshop but take less time to install on the plot
What raises the cost
- panels from abroad: delivery, customs clearance and a longer wait for the kit
- tight access, where the panels are made smaller and some are put up by hand
- design changes after the order: the panel is remade in the workshop
What lowers the cost
- a series of identical houses from one set of drawings
- a simple rectangular plan and a gable roof
- a level plot by the road, where the crane can stand next to the foundations
We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.
Get an estimateGuarantees
Panel installation, joints, the roof and windows carry a 2-year warranty. If we laid the water pipes, drains and wiring in the walls and floors, they have a 5-year warranty. The panels themselves and the materials carry the manufacturer's warranty; we pass on its terms together with the handover file, which also holds the photos of the joints before they were covered.
Questions and answers
How much does a turnkey prefabricated timber frame house cost?
A turnkey prefabricated timber frame house costs from 1,470 ₾ per m², and the shell from 690 ₾ per m². The shell covers the foundations, walls and floors made of insulated panels, the roof, windows and assembly, and the turnkey price adds building services and finishing to that. The design is priced separately.
The total depends most on where the panels come from, how a crane can get to the plot, the level of finish and the building services. We send a preliminary estimate from the house plan within 24 hours on business days. The final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.
How is a modern prefabricated timber frame house different from an old panel cabin?
Old prefabricated summer cabins were often put together from thin panels filled with sawdust or a thin layer of insulation, with no membranes and no calculation of the connections. People lived in them in summer, and in winter they froze through and got damp.
A modern panel is built like a proper timber frame wall: kiln-dried timber, mineral wool through the full depth of the studs, a breather membrane outside and a vapour barrier inside. The panels are fixed to each other and to the foundations according to a seismic calculation, and you can live in a house like this all year round. All it has in common with the old cabin is the word “panel” in the name.
Can a prefabricated timber frame house be built if a crane can't reach the plot?
It can, but the panels will have to be smaller. Four or five people can put up a small wall panel by hand, and the floor is then built from separate joists on site. Installation takes longer, and some of the advantage of panel construction is lost.
Sometimes the crane can stand in the street and lift the panels over the fence. We decide this on site: we look at the width of the street, the wires and the distance to the house footprint. If none of the options works, it is more honest to build an ordinary timber frame on the plot: the timber travels in small bundles on any lorry.
Can the layout be changed after the panels have been ordered?
Internal partitions that don't carry the floor above are usually built on site, and they can be moved with hardly any loss. External walls are harder: a new opening or a moved window means the workshop remakes the panel, and the structural engineer checks that the shear wall hasn't been weakened.
Each change like this goes into a contract addendum with the price of the new panel and the time it takes to make. That's why we advise fixing the windows, doors and service entries at the sketch stage, while moving an opening costs nothing but the architect's time.
How can you check the quality of panels made in a factory?
We ask the manufacturer for photos of every panel before it is closed: mineral wool without gaps, the membrane without tears, fixings as per the drawing, moisture meter readings on the timber. You receive these photos with the weekly report.
On the plot, the site foreman checks the kit against the markings, measures the diagonals of the panels and checks whether they got wet in transit. We don't install a damaged or damp panel; the supplier replaces it. You can watch the acceptance over a video call or send your own technical supervision engineer.
Further reading
Send us the house plan: we'll check how it divides into panels and price the shell