RU EN KA
A light gauge steel house frame being assembled next to a finished block house

Wood-chip concrete house in Batumi: what to know before ordering blocks

You can build a wood-chip concrete house in Adjara, but the blocks will have to be brought in: we found neither production in Georgia nor sales in builders' merchant chains. Made from wood chips and cement, wood-chip concrete is warm and light and holds nails and screws, but it soaks up a lot of water, so it needs a high plinth, a protective facade and wide roof overhangs. The shell costs from 860 ₾ per m², more than aerated concrete because of delivery, and we always price a replacement alongside it.

from 860 ₾/m²shell per m²: high plinth, imported blocks with ring beams, floors, roof. The final price is confirmed once agreed.

  • Timeline: the shell of a 120 m² single-storey wood-chip concrete house usually takes 4–5 months, including the wait for the blocks
  • Warranty: The masonry and the plinth carry a 2-year warranty on the work
Get an estimate

Who it’s for

  • You want a warm wall with a wood aggregate, but without the upkeep that profiled timber needs

  • You've found a wood-chip concrete plant and want to know whether its blocks are worth bringing to Adjara

  • You're building a house on a dry plot and are ready to budget for a high plinth and a protective facade

  • You're planning a mountain house, where winters are colder and a warm wall is especially needed

  • You're comparing wood-chip concrete with aerated concrete and a timber frame on price and timing

What’s included

  • Plant check: test reports, samples, delivery costing
  • Ordering the full quantity of blocks with a margin for breakage
  • Foundations with a high concrete plinth and damp-proofing
  • Batch acceptance on the plot and storage under a shelter
  • Masonry with a seismic ring beam and concrete lintels
  • Floors on the ring beam and a roof with wide overhangs
  • Plaster on mesh on both sides, or a ventilated facade, as set out in the contract
  • Wiring in non-combustible corrugated conduit and photos of the runs for the handover file

Prices: wood-chip concrete

from 860 ₾/m²

WorkPrice
Wood-chip concrete house shell860–1 020 ₾/m²
Turnkey wood-chip concrete house1 860–2 040 ₾/m²
30 cm wood-chip concrete block wall masonry, with materials230–275 ₾/m²
Turnkey ETICS facade, with materials205–250 ₾/m²
Seismic ring beam on masonry (concrete, reinforcement, formwork)100–130 ₾/lin. m
Aerated concrete house shell750–900 ₾/m²
Timber frame house shell750–900 ₾/m²

shell per m²: high plinth, imported blocks with ring beams, floors, roof. The final price is confirmed once agreed.

A wood-chip concrete house is built from large blocks made of wood chips and cement; the material is also sold under the name arbolite. The chips are treated with mineralising agents so that the sugars in the wood don't stop the cement from setting, and in the finished block every chip is coated in cement stone. The wall is warm and light, holds nails and screws and is good at stopping sound. It has two weak points: wood-chip concrete absorbs a lot of water, and it is almost impossible to find in Georgia. In Adjara both of them matter.

Wood-chip concrete in Georgia: delivery and batch checks

We haven't found any wood-chip concrete production in Georgia, and the big builders' merchant chains don't stock it either. Blocks for a house are brought in from abroad to order, and delivery takes weeks. This affects both the price of the shell and the schedule: we build the foundations while the blocks are on their way, and start laying only once the whole quantity is on the plot. Quickly buying the missing pallets won't be possible.

The quality of wood-chip concrete depends heavily on the plant, so before ordering we ask for test reports on strength, density and water absorption, plus a few samples. We look at the chips: they should be needle-shaped and roughly the same size, without sawdust or shavings, which weaken the block. At a broken edge every chip should be wrapped in cement, with no voids or loose spots, and the corners of the block shouldn't crumble in your hands. We check the batch again on unloading.

Where wood-chip concrete fits in Adjara and where it doesn't

Wood-chip concrete makes sense for a one- or two-storey house on a dry plot, where the owner wants a warm wall with a wood aggregate and is prepared to budget for a protective facade. It suits a house you also visit in winter, because the wall warms up quickly. For a mountain house in Adjara, where winters are colder, this is especially noticeable, but getting imported blocks there is even harder, and this has to be taken into account from the start.

We don't use wood-chip concrete in a plinth or basement, in walls that stand in the ground, or in damp lowlands where water lies for weeks after a downpour. On the seafront it needs cladding with a ventilated air gap, because render there gets soaked too often. If delivery doesn't fit the budget, we suggest a replacement made from local materials.

Water: the main weakness of wood-chip concrete

Wood-chip concrete absorbs noticeably more water than aerated concrete and takes a long time to dry. A wet block loses strength, and if it stays damp for months, mould appears on it. So a wood-chip concrete house starts with a high concrete plinth: the blocks must sit on a damp-proof course above the splash zone of heavy rain, and in the mountains above the snow that lies by the walls as well. We make the roof overhangs wide, gutters are a must, and the paved apron slopes away from the house.

On site we keep the blocks on pallets under a shelter, not under plastic sheeting on the ground. Overnight and before rain, the laid masonry is covered on top and on the windward side. In bathrooms and the kitchen, the walls under tiles are protected with waterproofing over the full height of the wet zone, behind the sink as well.

Ring beams, floors and seismic loads

Wood-chip concrete is not very strong, and it handles point loads poorly. So beams and slabs never bear directly on the masonry: we pour a reinforced concrete ring beam along the top of the walls, and the lintels over windows are concrete too. Wood-chip concrete works best with a timber floor on joists resting on the ring beam. A heavy cast-in-place concrete slab goes only on a cast-in-place concrete frame.

For seismic design, the low weight of the walls helps: a lighter house takes less force in a tremor. But weak masonry without ties fails more easily, so the ring beam, the cores at the corners and by openings and the anchoring to the foundations are calculated by the structural engineer. We offer a two-storey wood-chip concrete house only with a concrete frame, using the blocks to fill the walls.

Facade and finishing

The open structure of wood-chip concrete lets air through, so the masonry is plastered on both sides, otherwise the wind blows through the wall. Plaster grips the coarse, porous surface well, and we lay mesh over the whole surface. Outside we use lime-cement render and vapour-permeable paint, inside gypsum or lime plaster. We don't put polystyrene or dense membranes on wood-chip concrete.

For walls exposed to wind-driven rain, a ventilated facade is more reliable: fibre cement or timber board cladding on a subframe, with a gap behind it where the masonry can dry out. How it differs from render over insulation is shown in our look at the two facade types. In our experience a 30 cm wood-chip concrete wall in Batumi usually doesn't need insulation, but the thermal calculation makes the final decision.

Fixings and wiring

This is where wood-chip concrete is more convenient than other blocks. It holds nails and screws without wall plugs, shelves and kitchen cabinets hang on ordinary fixings, and window frames are secured reliably. For the water heater and heavy appliances we still use long anchors or embedded fixings, because the block's strength is low.

In a wood-chip concrete wall we run the wiring in non-combustible corrugated conduit or metal pipe. Factory-made wood-chip concrete burns poorly, since the chips are coated in cement, but the wood aggregate is still there, and we don't want to take risks. Photos of the runs before plastering go into the handover file.

What can replace wood-chip concrete

If delivery doesn't fit the timeline or the budget, we price a replacement. Aerated concrete in a cast-in-place concrete frame gives similar warmth and is made in Georgia itself, but it doesn't hold nails. A timber frame with mineral wool goes up faster and also holds fixings; there is more on the page about timber frame houses. Closest to wood-chip concrete in composition is permanent formwork made of wood-cement blocks that are filled with concrete, but these blocks are also rare in Georgia, and we check supply before the design.

How much a wood-chip concrete house costs

The shell of a wood-chip concrete house costs from 860 ₾ per m²: foundations with a high plinth, walls of imported blocks with ring beams, floors and roof. The protective facade, windows, building services and finishing are priced separately. A turnkey wood-chip concrete house starts from 1,860 ₾ per m².

Wood-chip concrete costs more than other blocks because of delivery: a 30 cm wall laid with materials costs from 230 ₾ per m². For comparison, an aerated concrete shell and a timber frame house shell both start from 750 ₾ per m². A turnkey ETICS facade costs from 205 ₾ per m² of wall, and a seismic ring beam from 100 ₾ per linear metre.

The price moves with the cost of transport and the exchange rate on the order date, the height of the plinth, and the type of facade and floors. We send a preliminary estimate from the house plan within 24 hours on business days. The final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.

Stages and timelines

  1. Choosing the plant

    1–2 weeks

    We request test reports and samples, work out the delivery cost and order the whole quantity with a margin for breakage.

  2. High plinth

    1–1.5 months

    While the blocks are on their way, we build the foundations with a high concrete plinth and damp-proofing.

  3. Batch acceptance

    1–2 days

    We check blocks from different pallets and stack them on pallets under a shelter.

  4. Masonry and ring beams

    3–4 weeks per storey

    Masonry on thermal mortar, concrete lintels, a ring beam along the top of the walls and cores as designed.

  5. Floors and roof

    3–5 weeks

    Floors on the ring beam, a roof with wide overhangs and gutters.

  6. Plaster and facade

    1–2 months

    Plaster on mesh inside and out, or a ventilated facade with an air gap.

Local specifics in Batumi

Imported blocks change the whole schedule. A lorry with wood-chip concrete takes a long time to reach Batumi, and on the way it can be held up by the weather or a queue at the border, so we don't start laying until the full quantity has arrived, and we keep spare blocks for breakage. We unload straight under a shelter: one downpour over open pallets costs the blocks weeks of drying.

We plan the masonry and plastering for the dry months, so that the walls are covered on both sides before the autumn rains. If the blocks arrive late and the season is missed, we don't plaster a wet wall: the masonry is covered for the winter on top and on the windward side, and the finishing moves to spring. A lorry can't always reach mountain villages, so the blocks are transferred to a smaller vehicle there, and every transfer adds breakage, which is why we allow a larger breakage margin for the mountains.

Materials and brands

For walls we use factory-made structural wood-chip concrete, with the block strength and density set by the design. We lay 30 cm blocks on a thermal mortar with perlite, or on cement-sand mortar if the blocks are even and the joint comes out thin. Ring beams and lintels need reinforcement and concrete.

On the outside goes lime-cement render on alkali-resistant mesh, with a silicate or silicone-based paint that lets vapour through. For a ventilated facade, fibre cement boards or timber boards on an aluminium or stainless steel subframe work well. We don't combine wood-chip concrete with polystyrene or dense membranes.

What makes up the cost

Timeline: the shell of a 120 m² single-storey wood-chip concrete house usually takes 4–5 months, including the wait for the blocks

  • The exchange rate and transport cost on the date the blocks are ordered

What raises the cost

  • Delivery of the blocks from abroad and a margin for breakage
  • A high plinth on a damp plot or in the mountains
  • A ventilated facade on walls exposed to wind-driven rain
  • A cast-in-place concrete frame for a two-storey house

What lowers the cost

  • A single-storey house of simple shape on ring beams
  • A timber floor instead of a cast-in-place concrete slab

We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.

Get an estimate

Guarantees

The masonry and the plinth carry a 2-year warranty on the work. Concealed pipes and wiring in the walls and floors have a 5-year term, if we installed them. The wood-chip concrete itself is covered by the plant's warranty, and we hand over the batch test reports and documents in the handover file.

Questions and answers

How much does it cost to build a wood-chip concrete house?

The shell of a wood-chip concrete house costs from 860 ₾ per m²: foundations with a high plinth, walls of imported blocks with ring beams, floors and roof. The protective facade, windows, building services and finishing are not included in this price. A turnkey wood-chip concrete house comes out from 1,860 ₾ per m².

Wood-chip concrete costs more than aerated concrete mainly because of delivery, and its price depends on the plant and the order date. We send a preliminary estimate from the plan within 24 hours on business days. The final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.

Does wood-chip concrete rot in a humid climate?

Factory-made wood-chip concrete with mineralised chips doesn't rot as long as it isn't left wet: every chip is coated in cement. Problems start when a block stays damp for months. It loses strength, mould appears on the surface, and a backyard-made block with poorly treated chips can deteriorate inside as well.

So in Batumi's humid climate wood-chip concrete needs a high plinth with damp-proofing, protection of the walls on both sides and wide roof overhangs. And before any of this, factory test reports for the blocks: without them we don't accept the material.

Can wood-chip concrete be left unplastered?

Not on the outside. The open structure of the block lets air and water through, the wind blows through the wall, and after wind-driven rain the masonry takes a long time to dry. The simplest solution outside is render on mesh with vapour-permeable paint; by the sea a ventilated facade with an air gap is better.

Plaster is needed inside too, at least a thin coat for painting. Without it, air passes through the wall into the room, and the heating and air conditioning work for nothing. Some people suggest leaving the blocks exposed for the look of wood, but the chips in wood-chip concrete look nothing like a timber wall, and crumbs fall from an exposed surface.

Does wood-chip concrete burn?

Factory-made wood-chip concrete burns poorly: the chips in it are wrapped in cement and do little to support combustion. But it is still a material with a wood aggregate, so we check its fire class in the plant's documents rather than taking it on trust. A backyard-made block with coarse chips and little cement behaves worse in a fire.

That is why in a wood-chip concrete house we run the wiring in non-combustible corrugated conduit or metal pipe, and around a stove or fireplace we use non-combustible finishes and the fire clearances that the design specifies. Plaster on both sides gives the blocks extra protection from fire.

What kind of floor should a wood-chip concrete house have?

Wood-chip concrete works best with a timber floor on joists: it is light, and the joists rest on the concrete ring beam along the top of the walls rather than on the blocks themselves. That way the load spreads along the whole length of the wall. The ring beam also ties the walls together, which matters for seismic resistance.

A cast-in-place concrete slab is heavier, and we don't put one on wood-chip concrete masonry. If the design needs a concrete slab, for example under a usable roof terrace or a second storey, we build the house in a cast-in-place concrete frame and fill the walls with wood-chip concrete. The structural engineer decides, based on the calculation.

Further reading

Send us the house plan and the plant's details, and we'll price wood-chip concrete with delivery, plus an alternative

We reply within an hour during business hours. Message us or leave a request: we’ll call you back, go over the details and suggest the next step.

Mon–Fri 10:00–19:00, Sat 11:00–16:00

Estimate within one business day

Step 1 of 3
Property type
Current condition
Step 2 of 3
When to start
    Step 3 of 3
    Preferred contact method

    How would you like to reach us?

    We’ll call you back at a time that suits you

    Preferred contact method
    Best time to call

    Search the site