Log house in Adjara and Batumi: machine-rounded logs, settling and cost

We build machine-rounded log houses from Ø220–240 mm logs ordered to the design: walls with a lateral groove, saddle notches at the corners, dowels up the height of the wall. A log house settles more than square timber, so windows, building services and finishing are done after settling. Such a house suits mountain Adjara and wooded plots best, and it also works well for a bathhouse or guest cabin. The log shell with foundations and roof costs from 1,620 ₾ per m².

from 1 620 ₾/m²foundations, Ø220–240 mm log walls and roof, excluding windows, utilities and finishing. The final price is confirmed once agreed.

  • Timeline: a 120 m² log house with its roof usually takes 2–3 months, followed by a settling period of 6–12 months before windows and finishing
  • Warranty: Log wall assembly and our other work carry a 2-year warranty
Get an estimate

Who it’s for

  • A plot in a mountain village in Adjara, and you want a log house with log ends projecting at the corners

  • You need a log bathhouse next to the house, and there is someone to fire it up and check on it

  • You are ready to wait a year for finishing to have log walls inside

  • You have bought a wooded plot above the coast and want a house that doesn't clash with the forest

  • You are comparing logs and square timber and want to know which works out cheaper turnkey

What’s included

  • A check of the log house design: diameter, notches, gables, anchoring for seismic loads
  • Ordering logs to the design, marked and with the notches cut
  • Checking the access for a long-bed lorry and the unloading area
  • Acceptance with a moisture meter, with preservative and end-grain treatment straight after unloading
  • Foundations with damp-proofing and the sill log
  • Assembly of the log walls with insulation and dowels, and framed gables
  • A roof on sliding brackets with overhangs covering the projecting log ends
  • Windows in settling frames, chinking and finishing after settling

Prices: machine-rounded logs

from 1 620 ₾/m²

WorkPrice
Machine-rounded log house shell1 620–1 980 ₾/m²
Turnkey machine-rounded log house2 610–3 120 ₾/m²
Ø220–240 mm machine-rounded log wall, with materials and assembly (per m² of wall)390–480 ₾/m²
Sealing the joints between wall courses (chinking), with materials17–24 ₾/lin. m
Preservative and fire-retardant treatment of timber structures20–30 ₾/m²
Timber lacquering or oiling27–36 ₾/m²
Profiled timber house shell1 200–1 440 ₾/m²
Glulam house shell1 980–2 400 ₾/m²

foundations, Ø220–240 mm log walls and roof, excluding windows, utilities and finishing. The final price is confirmed once agreed.

Machine-rounded logs are made on a machine that strips the bark and the uneven outer layer from the trunk, so that all the logs come out the same diameter. A log house built from them goes up quickly, the walls are straight from the start, and the log ends projecting at the corners give the look people choose such a house for. You can build a machine-rounded log house in Adjara, but compared with square timber it settles more and has more places where water gets in.

How a machine-rounded log wall is built

Along the underside of each log runs a lateral groove, a half-moon channel cut along its whole length. Each log sits with this groove on the log below, insulation between the courses is laid between them, and the rows are fixed together with dowels. At the corners the machine cuts saddle notches, and the logs are joined with their ends left projecting: they extend beyond the wall and keep the corner from shifting.

Along the top of the log, in the part hidden under the next course, a relief kerf is cut. As the log dries, the stress goes into this kerf, and fewer large cracks appear on the visible faces. How warm the wall is depends on the width of the lateral groove rather than the thickest part of the log, so at the joint the wall is thinner than the log's diameter. The first course, the sill log, is often made of square timber or of a log sawn lengthwise, so that the log walls sit flat on the plinth.

Green or dried logs: ordering and acceptance

Rounded logs are more often made from timber at natural moisture content: kiln-drying a trunk of that diameter is slow and costly, and dried logs are noticeably more expensive. For a house on the coast we still recommend kiln-dried logs, and we keep green logs for the mountains and for small buildings: in the humid air by the sea a green log house takes too long to dry. We order the logs from the manufacturer to the design, with the notches already cut and every log marked. Where the batch comes from and who makes it is stated in the estimate, as some of these logs are imported. We ask the supplier for the moisture content before dispatch and measure it ourselves on acceptance.

The machine removes the outer layer of the trunk, the densest and most resinous one. Without it a log soaks up water more easily and turns blue faster if it lies in the rain. So straight after unloading, the logs are treated with a preservative that protects against beetles, the ends are sealed with an end-grain sealer, and the logs are stacked on spacers under cover, with gaps between the rows.

Settling of a log house: what we allow for

A log house settles noticeably more than kiln-dried square timber, especially one built from logs at natural moisture content, and in Batumi's humid air the settling drags on for months. So the order is this: we assemble the walls, put on the roof, and the house stands under it and dries. Windows, building services and finishing are done after settling, and that is how the scope of the shell is written.

  • Gables are more often framed: a log gable is tall, stands up poorly to wind and settles along with the walls.
  • The rafters go on sliding brackets, so that the wall can move down under the roof without dragging it along. We use a light roof covering, and our comparison of metal roof tiles and asphalt shingles will help you choose between the two.
  • Openings are cut with grooves for the settling frames, and the windows go into these frames after the settling period.

Screw jacks under the posts and slip joints on the partitions work the same way as in a house built from profiled timber, only a log house needs a larger height allowance. After the main settling we seal the joints on the outside with chinking, the “warm joint”, and in a log house it matters more than in a timber one: on a rounded joint, wind-driven rain gets into the groove more easily than on a flat one.

Log ends, notches and projections: where a log gets wet

At every corner of a log house the log ends stick out, and the rain hits them on the end grain. End grain soaks up water much more than the side of the log, and rot in log houses often starts at the projecting ends and the bottom notches. So:

  • we make the roof overhangs deep enough to cover the projecting log ends at the corners;
  • the ends get a separate sealer that slows down their drying and keeps the rain out, so they crack less;
  • during assembly the notches are treated with preservative and lined with insulation, so that water doesn't sit in the corner;
  • under the windows we fit drip sills that project beyond the face of the log.

The sill log goes on damp-proofing on top of a plinth 30–40 cm high, and for a log house we stick to the upper figure: the projecting ends and bottom courses are bare wood in the splash zone. The foundations for a log house are chosen according to the ground survey, usually a strip footing or a slab, and piles on a slope. A log house is light, and in a tremor the main danger for it is sliding: the wall can shift off the plinth or come apart along the courses. So the anchoring to the foundations and the dowels up the height of the wall are calculated by the structural engineer.

Delivery and assembly in the mountains and by the sea

The logs for a log house are long and travel on a long-bed lorry. Such a vehicle can't always reach a plot in mountain Adjara: hairpin bends, bridges and narrow village streets mean the logs have to be transferred to a smaller vehicle, and sometimes unloaded further down and lifted with a lorry-mounted crane. We check the access, the unloading area and the storage space before ordering.

A small crew assembles the log house following the markings, and heavy logs are lifted by crane. We start assembly in spring, so that by the autumn rains or the first snow the log house stands under its roof. What else changes when building high in the mountains, from snow loads to off-grid utilities, is described on the page about building a house in the mountains.

Finishing inside a log house

Inside, the logs are usually left exposed. After settling they are sanded, large cracks are filled, and then the walls are coated with an interior oil or lacquer. For the kitchen, the bathroom tiles and built-in wardrobes we put up a separate frame with a gap at the top, as in a profiled timber house, only for logs we leave a larger settling allowance.

A round log is poor at hiding cable, so the wiring in a log house is more often surface-mounted: retro twisted cable on ceramic insulators, or steel conduit along the wall. It can be concealed only in steel conduit inside a channel drilled during assembly, and then the socket positions are marked as early as the design. The floor is laid on joists, and under the bathroom tiles we make a separate waterproofed base that isn't connected to the logs.

Machine-rounded log house: where it fits

A log house suits a plot in the woods or in the mountains best, one the owner visits often: a mountain village, a wooded slope above the coast, a country plot by a river. Logs also work well for small buildings, such as a bathhouse or a guest cabin. The steam room, stove and drainage in a stand-alone bathhouse are covered on the page about building a bathhouse.

A log house is a poorer fit for a narrow town plot: the log ends at the corners project beyond the wall, and there may not be enough room left for the setbacks from the neighbours. Right by the sea, the projecting ends and end grain under wind-driven rain need frequent care. If you need a timber house for living in all year round without a long settling period, glulam behaves more predictably: it costs more, but hardly settles.

How much a machine-rounded log house costs

The shell of a machine-rounded log house costs from 1,620 to 1,980 ₾ per m² of floor area. That covers the foundations, the assembled log walls, the floors and the roof with rafters. Windows, utilities and finishing are not included in this price: they are done after settling and priced separately, as is the design. A turnkey log house starts from 2,610 ₾ per m².

The biggest line in a log house estimate is the wall: from 390 ₾ per m² including the logs and assembly. Everything else is inexpensive taken separately, but it adds up. Sealing the joints between the courses starts from 17 ₾ per linear metre, and a log house has a lot of joints; preservative and fire-retardant treatment from 20 ₾ per m² of surface; a finishing oil or lacquer from 27 ₾. A profiled timber shell is cheaper, from 1,200 ₾ per m²: a metre of wall takes more log, and the notches and offcuts add to the price.

Costs go up with kiln-dried logs, a larger diameter, a roof with several gables and a road where the logs have to be transferred to another vehicle. A simple log house with a gable roof and framed gables, and a plot by the road, cost less. We send a preliminary estimate from a sketch and photos of the plot within 24 hours on business days, and the final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.

Stages and timelines

  1. Design and log order

    1–2 months

    The structural engineer checks the log walls and joints, and the supplier prepares the logs with notches and markings to the design.

  2. Foundations and sill log

    2–4 weeks

    The foundation type is chosen from the ground survey, then topped with damp-proofing, anchors and the sill log.

  3. Log wall assembly

    3–6 weeks

    The logs go onto the insulation following the markings, the rows are fixed with dowels, and grooves for the settling frames are left in the openings. Ends and notches are treated as assembly goes on.

  4. Roof and gables

    2–4 weeks

    We build the framed gables, set the rafters on sliding brackets, put on the roof covering and hang the gutters.

  5. Settling period

    6–12 months

    The log house dries under its roof. Every few weeks we check the screw jacks and use a moisture meter to see how the moisture in the walls is falling.

  6. Windows, services, finishing

    2–4 months

    Settling frames and windows, chinking, wiring, bathrooms on a separate base, sanding and coating the walls.

Local specifics in Batumi

There are more timber houses in the mountain villages of Adjara than on the coast, and a log house doesn't look out of place there. What gets in the way of building is the short season, the snow and roads that wash out after a downpour. A log house assembled over the summer spends the winter under its roof, and the first winter goes on settling.

On the coast, the problem for logs is damp. A house built from logs at natural moisture content dries slowly in the humid air, and in the rainy months from September to January it hardly dries at all. So we allow extra time for settling and fit the windows according to moisture readings from the walls, not the calendar.

The sea wind brings salt, and in a log house the metal suffers first: cramps, anchors, the fixings of the drip sills. We use stainless steel for these. We keep trees and shrubs away from the walls so that air can reach the bottom courses.

Materials and brands

The log walls are assembled from machine-rounded softwood logs, most often pine, spruce or larch, 220–240 mm in diameter, with a lateral groove, a relief kerf and machine-cut saddle notches. The sill log is larch or treated square timber. Between the courses we lay a jute or linen strip, the rows are fixed with timber dowels, and for the chinking we use an elastic timber sealant.

The preservative, the end-grain sealer and the finishing oil or exterior wood stain are chosen from their technical data sheets among the products sold in Georgia. Windows are more often uPVC on VEKA profiles, and the roof is kept light: metal roof tiles or asphalt shingles.

What makes up the cost

Timeline: a 120 m² log house with its roof usually takes 2–3 months, followed by a settling period of 6–12 months before windows and finishing

  • the settling period: the longer the log house dries, the later finishing starts

What raises the cost

  • kiln-dried logs instead of logs at natural moisture content
  • a larger log diameter for a house lived in all year round
  • several gables and a complex roof
  • a mountain road on which a long-bed lorry can't reach the plot

What lowers the cost

  • a simple rectangular log house with a gable roof
  • framed gables instead of log ones

We prepare the exact estimate from measurements and photos. It’s free and comes with no obligation.

Get an estimate

Guarantees

Log wall assembly and our other work carry a 2-year warranty. A 5-year term applies to the water pipes, drains and wiring in the walls and floors, if we laid them. The logs, windows and finishes carry the manufacturer's warranty. Drying cracks in the logs and adjusting the screw jacks are part of looking after a log house, and we set out the inspection schedule in the handover file.

Questions and answers

How much does a turnkey machine-rounded log house cost?

Turnkey from 2,610 ₾ per m², and the shell from 1,620 ₾: foundations, assembled log walls, floors and roof. The shell doesn't include windows, utilities or finishing, which are done after settling, and the design is also priced separately.

What moves the price is how the logs are dried and their diameter, the shape of the roof and the road to the plot. We send a preliminary estimate from a sketch within 24 hours on business days. The final cost is set on the basis of the design, after a visit to the plot and once the estimate is agreed.

What log diameter should I choose for a house?

How warm the wall is depends not on the diameter but on the width of the lateral groove: at the joint a log is noticeably thinner than in the middle. For a bathhouse, a guest cabin or a summer house we usually find 220 mm logs are enough, a house lived in all year round we build from 240 mm, and in either case the wall is checked by a thermal calculation.

Thicker isn't always better. A larger-diameter log costs more, is heavier to assemble and takes longer to dry, which means it takes longer to settle. In the mountains it sometimes makes more sense to insulate a 240 mm log wall on the outside under cladding than to order bigger logs and wait an extra season for them to settle.

Why do machine-rounded logs crack?

A log dries faster on the outside than at the core, and the outer layers shrink first. The stress comes out as cracks along the grain, and they can't be avoided altogether, especially in logs at natural moisture content. The relief kerf directs the main crack to where the next course will cover it.

Small cracks on the facade are harmless as long as water doesn't sit in them. After settling, a deep crack on the rain side is filled with timber sealant and covered with the finish. Fierce heating in the first winter adds cracks, so we warm the house up gradually.

How are machine-rounded logs different from hand-cut logs?

Hand-cut logs are worked by hand: the bark is removed but the dense outer layer is kept, and the notches and grooves are cut with an axe on site. The logs vary in diameter, so the log house comes out uneven and lively to look at, and it takes longer and costs more to build. Machine-rounded logs are made on a machine, all of the same diameter, and the house is assembled quickly following the markings.

The difference also shows in upkeep. A hand-cut log keeps its outer layer and soaks up water more slowly. A machine-rounded log has had this layer cut off, so it needs preservative and the first coat of facade finish straight after assembly, not a year later.

Can a machine-rounded log house have two storeys?

It can, but the settling of two storeys of logs adds up, and at the top it is more noticeable. So we more often build a storey and a half: log walls, with an attic floor under the rafters and framed gables. If you need a full upper storey, the staircase is fixed with a sliding top connection, and pipes and cables between the floors are left with a loop to allow for settling.

There is another option: a masonry ground floor and a log upper floor. The lower storey takes the damp near the ground, the log walls on top settle half as much in height, and the structural engineer designs the junction between the floors for seismic loads.

Further reading

Send us a sketch of the log house and photos of the road to the plot, and we'll price the shell within 24 hours

We reply within an hour during business hours. Message us or leave a request: we’ll call you back, go over the details and suggest the next step.

Mon–Fri 10:00–19:00, Sat 11:00–16:00

Estimate within one business day

Step 1 of 3
Property type
Current condition
Step 2 of 3
When to start
    Step 3 of 3
    Preferred contact method

    How would you like to reach us?

    We’ll call you back at a time that suits you

    Preferred contact method
    Best time to call

    Search the site